PMI Agile PMI-ACP Question # 142 Topic 15 Discussion

PMI-ACP Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?


A.

Escalated the issue to management


B.

Ensured the early engagement of key stakeholders


C.

Provided feedback to the architecture team to change the enterprise architecture standards


D.

Raised an exception for non-adherence to the enterprise architecture standards for this product