PMI Agile PMI-ACP Question # 146 Topic 15 Discussion

PMI-ACP Exam Topic 15 Question 146 Discussion:
Question #: 146
Topic #: 15

Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.

What should the Scrum Master do next?


A.

Alert the team that sprint goals might not be met and create an alternative plan


B.

Obtain team buy-in to perform modifications to the sprint backlog


C.

Have the sprint proceed as planned


D.

Ask the team to decide if the task should be reassigned