Question #: 148
Topic #: 15

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?


A.

Estimate only functional requirements that will impact product quality


B.

Add team resources


C.

Refer the issue to the product owner


D.

Break non-functional requirements into those that can be delivered in the given sprint