PMI Agile PMI-ACP Question # 152 Topic 16 Discussion

PMI-ACP Exam Topic 16 Question 152 Discussion:
Question #: 152
Topic #: 16

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?


A.

Evaluate how much can be delivered based on the Scrum Master's estimation


B.

Identify a set of user stories based on the team's velocity


C.

Initiate an estimation session


D.

Consult historical data for project completion