PMI Agile PMI-ACP Question # 23 Topic 3 Discussion

PMI-ACP Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?


A.

Keep sprints short.


B.

Invite the stakeholder to the daily stand ups.


C.

Ask the stakeholder for estimates for each user story.


D.

Schedule more demos during each sprint.