PMI Agile PMI-ACP Question # 50 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.

What should the team lead do next?


A.

Negotiate with the project director to reduce the types of tests for which they need details to reduce the impact of this request.


B.

Escalate this as an issue to the executive project sponsor for a decision because it will impact the ability of the team to deliver the product on time.


C.

Ask the test manager to provide a detailed estimate of the time required to write the plan for the solution and their capacity for the remainder of the week.


D.

Ask the team to put their work on hold and collaborate on the documentation because it can be completed quicker if everyone shares the work.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.