How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)
A.
Stated understanding of the release goal
B.
Complete vision of the end product
C.
Timeline of the project
D.
List of the user stories that will be part of the next releases
The release goal provides clarity on the purpose and objectives of the release. It helps stakeholders understand the value the team aims to deliver.
List of the user stories that will be part of the next releases
A well-defined list of user stories ensures that stakeholders know which features and functionalities are planned for upcoming releases.