PMI Agile PMI-ACP Question # 57 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?


A.

Ensure the teams are working together daily throughout the product development and are keeping the team's progress up to date.


B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.


C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.


D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.