PMI Agile PMI-ACP Question # 77 Topic 8 Discussion

PMI-ACP Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

During sprints, the development team members are frequently invited to various meetings to provide technical opinions, consuming the team's working time and causing compliance issues. Which action should the scrum master take to address this situation?


A.

Request additional resources to prevent compliance issues while still fostering a collaborative workplace.


B.

Escalate the concern to the product owner and request that they prioritize the development work.


C.

Designate a single team member to attend the meetings and establish a capacity buffer for each sprint.


D.

Reject all external meetings for the development team so they can fully focus on their sprint tasks.