Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMI-ACP All Questions
Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

PMI Agile PMI-ACP Question # 88 Topic 9 Discussion

PMI-ACP Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

What should be done with this story?


A.

Mark it as incomplete and prioritize it for the next sprint


B.

Mark it as complete, since the product owner has the final say


C.

Discard it and create a new story for the remaining scope of work


D.

Mark it as complete, since the team completed the scope of work


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.