PMI Professional in Business Analysis PMI-PBA Question # 19 Topic 2 Discussion

PMI-PBA Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?


A.

The product was not adequately tested in accordance with the test plan.


B.

The requirements matrix did not adequately track back to client requirements.


C.

Requirement changes were not properly identified in the project charter.


D.

The product design was not properly reviewed by the quality department.