PMI Professional in Business Analysis PMI-PBA Question # 23 Topic 3 Discussion

PMI-PBA Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.

This situation could have been averted if:


A.

quality attributes were captured and tested.


B.

critical business requirements were accommodated and tested.


C.

nonfunctional requirements were identified and tested.


D.

essential product requirements were captured and tested.