PMI Professional in Business Analysis PMI-PBA Question # 42 Topic 5 Discussion

PMI-PBA Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

When a change request is received, the business analyst is responsible for:


A.

analyzing the impact to the project schedule and budget.


B.

ensuring that change-related incidents are minimized in production.


C.

analyzing the impact on business and underlying systems.


D.

prioritizing and scheduling the changes requested.