PMI Professional in Business Analysis PMI-PBA Question # 44 Topic 5 Discussion

PMI-PBA Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

Which document best provides the boundaries for product development?


A.

Scope definition


B.

Requirements baseline


C.

Project plan


D.

Scope document