PMI PMI-PMOCP Question # 2 Topic 1 Discussion

PMI-PMOCP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

An organization delivers system implementation projects to external clients. The PMO has noticed that recent post-project reviews consistently reveal issues. Further analysis shows that these issues become apparent during end-user testing. The testing process is unstructured and usually lacks documentation.

What next steps should the PMO lead take?


A.

Create a test strategy to be referenced by project teams to support the system-testing process alignment.


B.

Mandate that all project testing issues be logged and reviewed before agreeing on how each item should be addressed.


C.

Deploy a test management tool that should be used by all system implementation project teams.


D.

Assess the organizational project management (OPM) maturity gaps and enhance the test management process.