Question #: 23
Topic #: 3

An enterprise organization recently initiated a new project. A PMO professional made sure that all pertinent project documentation was prepared and that all project management procedures were carried out in accordance with the accepted practices.

What source should the PMO professional use to identify stakeholders?


A.

The plan for managing communications to gather information about project stakeholders.


B.

The job descriptions and the amount of experience required for potential stakeholders.


C.

The information about the project's stakeholders that is included in the business documentation.


D.

The necessary management approaches and measures needed to properly include stakeholders.