Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?
PRINCE2 is predictive, but not emergent
PRINCE2 is predictive and can be emergent
PRINCE2 requires a lengthy start to a project
PRINCE2 requires a disruptive start to a project