Questions # 1:

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Expert Solution
Questions # 2:

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

Options:

A.

To use empiricism, based on knowledge that comes from experience

B.

To build, measure, learn from your experiences

C.

To create a minimum viable product to manage uncertainty

D.

To fail fast, if you are going to fail

Expert Solution
Questions # 3:

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

Options:

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

Expert Solution
Questions # 4:

Which is a key objective of running a workshop?

Options:

A.

To make daily progress visible to the delivery team and key stakeholders

B.

To encourage collaboration and create the defined outputs from the event

C.

To communicate decisions to the wider stakeholder community

D.

To make day-to-day decisions on behalf of the delivery team within a sprint

Expert Solution
Questions # 5:

Which statement about the waterfall methodology definition is CORRECT?

Options:

A.

It prevents earlier phases of development being revisited

B.

It uses an iterative and incremental approach

C.

It focuses on responding to changing requirements

D.

It delivers products more frequently in shorter phases

Expert Solution
Questions # 6:

Which statement about the ‘directing a project’ process is CORRECT?

Options:

A.

The project board may pull reports from the information radiator

B.

As a minimum, the project board should receive oral reports from the project manager

C.

The project board should attend the delivery team’s daily stand up meeting

D.

The project board should receive regular reports focusing on cost and time overruns

Expert Solution
Questions # 7:

Which statement defines a PRINCE2 principle?

Options:

A.

A PRINCE2 project defines its quality management approach

B.

A PRINCE2 project is monitored and controlled on a stage-by-stage basis

C.

A PRINCE2 project ensures a consistent approach to risk management

D.

A PRINCE2 project is tailored to suit the competitor’s environment

Expert Solution
Questions # 8:

Which is typically used in agile when estimating detailed requirements during sprint planning?

Options:

A.

Rationalism

B.

Trading

C.

Visioning

D.

T-shirt sizing

Expert Solution
Questions # 9:

Which statement about timeboxes is CORRECT?

Options:

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments

Expert Solution
Questions # 10:

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

Options:

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Expert Solution