Which is a key objective of running a workshop?
To make daily progress visible to the delivery team and key stakeholders
To encourage collaboration and create the defined outputs from the event
To communicate decisions to the wider stakeholder community
To make day-to-day decisions on behalf of the delivery team within a sprint