View all questions & answers for the PRINCE2-Agile-Foundation exam
Which statement about the ‘directing a project’ process is CORRECT?
The project board may pull reports from the information radiator
As a minimum, the project board should receive oral reports from the project manager
The project board should attend the delivery team’s daily stand up meeting
The project board should receive regular reports focusing on cost and time overruns
Submit