PRINCE2 Agile PRINCE2-Agile-Foundation Question # 13 Topic 2 Discussion

PRINCE2-Agile-Foundation Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

Which statement about the ‘keep teams stable’ target is CORRECT?


A.

It applies primarily to the long term, such as a project or a program


B.

It is the primary reason why the tolerance for cost is set to zero


C.

It prevents compromising the overall quality level of the product


D.

It results in the early delivery of a minimum viable product