An Agile Release Train prepares for PI Planning. They have both Features and Program Epics among the desirable items for this PI. However, Product Management is stuck because some Epics are too big and won't fit in this PI.
A.
Pick only those Epics that have clearly defined success criteria and might fit into the PI.
B.
Split Epics into Features and prioritize the Features to determine what should go into the PI.
C.
Split Epics into Features and use capacity allocation to determine what should go into the PI.
D.
Instead of planning just the upcoming PI, plan for a longer period to cover the full duration of the Program Epics.