Scrum Professional Scrum with Kanban PSK-I Question # 1 Topic 1 Discussion

PSK-I Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

What is a probabilistic forecast intended to communicate?

(choose the best answer)


A.

The best way to predict the future performance of a team.


B.

A guarantee of when a certain amount of scope will be complete.


C.

A forecast based on past performance that can help discussions about the likelihood

of achieving a certain goal in a given time frame.