Scrum Professional Scrum with Kanban PSK-I Question # 3 Topic 1 Discussion

PSK-I Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?


A.

The team promises to have 85% of all Product Backlog items done within 5 days.


B.

The team can get any critical system backup within 5 days.


C.

The team expects they will complete a work item within 5 days of when they start working on it 85% of the time.


D.

In the last Sprint, the team has been able to complete 85% of Product Backlog items within 5 days of starting work on the item.