An SLE of 85% for 5 days signifies that the team anticipates they will complete items within 5 days, 85% of the time. This helps set clear expectations with stakeholders, ensuring transparency around potential delivery timelines. The SLE is based on historical data and provides a probability-based forecast, rather than a commitment. References: The Kanban Guide for Scrum Teams​.