Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 10 Topic 2 Discussion

PSK-I Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

In the context of Scrum, which of the following statements about Cycle Time are true?

(Choose the best two answers)


A.

Cycle Time should be exactly the length of a Sprint.


B.

Cycle Time for some Product Backlog items might be longer than a length of Sprint.


C.

Average Cycle Time should be shorter than a length of Sprint.