Questions # 41:

The first step in creating a schedule is to…

Options:

A.

Create the WBS

B.

Create the RBS

C.

Estimate task durations

D.

Estimate project duration

Expert Solution
Questions # 42:

A milestone is…

Options:

A.

A major element or step of a project

B.

An individual task to be completed in a project

C.

The final task of a project

D.

Time allotted for each task

Expert Solution
Questions # 43:

True or False: Risks are always negative.

Options:

A.

True

B.

False

Expert Solution
Questions # 44:

Which of the following skills is crucial for a project manager?

Options:

A.

Able to multi-task

B.

Able to manage competing demands

C.

Self-confidence

D.

All of the above

Expert Solution
Questions # 45:

The Task Force Team Model is one that:

Options:

A.

Has a designated leader but includes sharing of responsibility

B.

Manages itself because no one person has authority

C.

Comes together for a specific time to work on a specific task

D.

to identify the sequence of events involved in the failure]

Expert Solution
Questions # 46:

What should you do with e-mails that you won’t refer to in the future?

Options:

A.

Archive them on a CD or some other electronic storage

B.

Delete them

C.

Print them off and file them with your archive files

D.

Mark them as a spam

Expert Solution
Questions # 47:

Which of the following is not a component of the knowledge management mix?

Options:

A.

Experts

B.

People

C.

Technology

D.

Processes

Expert Solution
Questions # 48:

All teams have:

Options:

A.

Specific meeting times

B.

One leader for everyone

C.

Ground rules that are agreed on beforehand

D.

Outing Schedule

Expert Solution
Questions # 49:

Which of the following is a way for a project to end?

Options:

A.

Extinction

B.

Inclusion

C.

Integration

D.

Any of the above

Expert Solution
Questions # 50:

Teams that rarely see each other face-to-face are defined by:

Options:

A.

The Cutting Edge Model

B.

The Cyber Team Model

C.

The Task Force Model

D.

The Core Group Model

Expert Solution