An organisation (ABC) plans to carry out a second-party audit of the environmental management system of a supplier (XYZ). Both, ABC and XYZ, have a certified Environmental Management System (EMS) to ISO 14001 by the same certification body.
Which one of these statements is correct?
Which one of the following outcomes of an audit does not require the auditee to respond?
Whistlekleen is a national dry cleaning and laundry organisation with 50 shops. You are conducting an EMS surveillance audit of Head Office and are sampling environmental performance measurement. You find that 80 per cent of failures to meet performance criteria originate from five shops in the same region. Most of these failures relate to the release of volatile organic compounds (VOCs) that exceeded regulations. The Environmental Manager tells you that these are the oldest shops in the organisation. The cleaning equipment needs replacing but the organisation cannot afford it at the moment.
On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.
When reviewing the nonconformity report files, you find that the organisation is facing a legal dispute with the environmental authority over multiple breaches of environmental legislation.
Select the three best options for how this dispute should be handled by the organisation through its EMS.
A group of 22 Italian restaurants in downtown San Francisco (US) established an EMS following the requirements of ISO 14001. You are performing an internal audit before the fourth certification cycle. The audit plan included an audit of the General Manager (GM) as the last interview before the closing meeting. During the interview with the GM, you audit clause 10.3 (Continual improvement). The dialogue is as follows.
You: Could you please tell me how did you improve the EMS to enhance environmental performance (Clause 10.3)?
GM: One way to improve the EMS is to improve one or several of its processes. We decided to improve the water-consuming processes in all our branches. We use water in many of our processes (e.g. to wash our kitchens, our cutlery, plates, and glasses, to keep our floors clean). The idea was to review these processes in detail to reduce the amount of water used per customer. Each of the 22 branches sent us their results, we analysed the data and found out that the average water consumption per customer was reduced by 13%; therefore, we improved our environmental performance. We are happy about that.
You: What about the results in each branch?
GM: Have a look at this table:
Analysing this table, what would be your decision related to raising nonconformities to clause 10.3? Select two.
Which one of the following outcomes of an audit does not require the auditee to respond?
A small services organisation has been contracted to handle the disposal of waste for a local hospital. You are an auditor conducting a Stage 2 audit of the care home to ISO 14001. You are reviewing the contract with the Service Manager (SM). An addendum to the contract only requires that biological waste is disposed of in the most environmentally friendly way, without reference to any regulatory requirements.
You: How was the waste disposal plan for the contract developed?
SM: We have a basic template that covers the materials, labour requirements and methods to be employed. Some of that is specified by the contractor.
You: How does the plan deal with specific items like biological waste, which are included in the contract and can pose biological hazards to the environment?
SM: The basic plan covers general waste, but we have an addendum that covers biological waste.
You: Are you aware of the regulatory requirements for waste disposal standards in hospitals?
SM: Yes but we depend on the contractor to look after that side of things.
You raise a nonconformity against section 8.1.d of ISO 14001.
At the Stage 2 closing meeting of the audit, the EMS Manager objects to the nonconformity raised and asks for it to be withdrawn. He insists that they meet all the regulations.
Choose one of the options that the audit team leader should take in response to the request.
An audit team leader arrives at a steel fabrication organisation that manufactures fire escape stairs to carry out a Stage 2 certification audit. At a meeting with the EMS Manager, she is told that they have won their biggest contract from a construction organisation to manufacture and install fire escape stairs. They appointed a subcontractor to perform the installation work. The EMS Manager wants the ISO 14001 audit extended to cover the installation site.
Select which one of the options is the correct response by the auditor.
A management system meeting ISO 14001:2015 requirements is based on the Plan-Do-Check-Act (PDCA) cycle.
Which two elements of the management system are part of the 'Check' stage of the PDCA cycle?
Showitoff is an organisation specialising in the design and production of wall decorating materials for the domestic market. During an ISO 14001 certification audit of the site, the auditor comes across an open, walled area just outside the maintenance department. It contains various scraps of wood and metal as well as several rusty components. They are lying on an oily floor. When asked about it, the EMS Manager states that he presumes that the materials come from maintenance work.
The auditor interviews the Maintenance Manager in his department. He notes that shelves containing various spares are well labelled and neatly stacked. He asked about the "dump" outside and is told that it contains some excess materials that the Manager likes to keep in case they come in handy at some stage. The auditor points out that the "dump" might be classed under regulations as a landfill site, which requires an operating licence. The Maintenance Manager is not aware of such a licence.
The auditor decides to review the process for evaluation of compliance with environmental regulations in more depth.
Select three options that provide a meaningful audit trail for this process.
Sparkle is an organisation that provides mobile car cleaning services at customers' premises. It has been certified to ISO 14001 for some time and has appointed a full-time Environmental Management System Manager. The audit plan during a surveillance audit includes continual improvement and the auditor asks to see the most recent management review meeting minutes.
The minutes indicate that the Environmental Management System Manager reported that the last review of the organisation's environmental legislation register was made three years ago instead of annually as planned in the Environmental Management System. At that time, he asked for finances to employ a legislation expert to update the register but was denied the request by top management on the basis that it was unlikely that many changes to legislation had occurred. No related improvement actions were documented in the minutes.
Based on the scenario, select the two options which best describe the evidence for raising such a non-conformity.