Questions # 11:

Which one is true for Sprint Planning?

Options:

A.

The work to be performed in the Sprint is planned

B.

Demo of the previous increment is done

C.

Customers will share the feedback

D.

The Product Backlog is refined

Questions # 12:

A Scrum Team with all the skills necessary to deliver a usable Increment is

Options:

A.

Divided into sub-teams.

B.

Distributed.

C.

Cross-functional.

D.

Difficult to manage.

Questions # 13:

What is one accountability of a Scrum Master?

Options:

A.

Set the budget

B.

Provide estimates

C.

Improve the Scrum Team’s effectiveness

D.

Decide when to release the product

Questions # 14:

When a Scrum Master encounters resistance from outside of the Scrum Team, what should the Scrum Master do?

Options:

A.

Escalate to management to reprimand the resisters

B.

Not intervene in the business of others

C.

Create a status update meeting for all Scrum Masters to coordinate team dependencies

D.

Work with other Scrum Masters to increase the effectiveness of the application of Scrum in the organization

Questions # 15:

How should Scrum teams plan work to be performed within Sprints?

Options:

A.

One release at a time, adjusting the number of Sprints to the prior releases’ average velocity

B.

One Sprint at a time, adapting each Sprint Backlog according to what was learned from the last Sprint

C.

One project at a time, adjusting each Sprint Backlog Item to meet the release date negotiated at inception

D.

One Sprint at a time in the Product Backlog Refinement meeting with participation of stakeholders