Questions # 1:

Your role is that of the Lead Enterprise Architect at a multinational automotive corporation. The company is headquartered in Germany, and manufactures cars, trucks and buses. It has manufacturing plants across North America, South America, Europe and Asia. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.

The company has an ongoing initiative to improve the efficiency of all of its production operations, and in particular to reduce its carbon footprint. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in energy usage could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in one central data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities.

The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are based on the TOGAF standard. At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the global

CIO. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.

You have been asked to select the most appropriate recommendation to ensure that the team evaluated different approaches to the problem and clarifies the requirements for the architecture.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

The team should identify the individuals and groups within the organization who will contribute to the project, in order to understand who has concerns about the initiative. The team should then hold a series of interviews at each of the manufacturing plants using the business scenario technique. This will then enable them to identify and document the key high-level stakeholder requirements for the architecture.

B.

The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier list. Based on the findings from the research, the team should define a preliminary Architecture Vison. The team should then use that model to build concerns among the key stakeholders.

C.

The team should perform a shallow architecture development iteration, developing Baseline and Target Architectures for each of the manufacturing plants. This should include development of a set of views corresponding to selected viewpoints that address key concerns of the stakeholders. A consolidated gap analysis between the architectures will then be used to validate the approach, and determine the capability increments needed to achieve t

D.

The team should utilize its approved supplier list, and conduct a pilot project that will enable those suppliers to demonstrate potential solutions that will address the concerns of the stakeholders. Based on the findings of that pilot project, a complete set or requirements will be developed that will drive the evolution of the architecture.

Expert Solution
Questions # 2:

Scenario: Sollace Manufacturing

Please read this scenario prior to answering the question

Sollace Manufacturing is a major supplier in the automotive industry, headquartered In Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.

Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff. The Sollace Manufacturing Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9. At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation. The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.

Refer to the Sollace Manufacturing Scenario

You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project. One of the earliest initiatives in the Enterprise Architecture program at Sollace Manufacturing was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.

You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution. [Note: You should assume that Sollace Manufacturing has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.] Based on TOGAF 9, which of the following is the best answer?

Options:

A.

Common-use Applications, Data is Shared, Data is Accessible, Data Security, Interoperability, Control Technical Diversity

B.

Business Continuity, Service-orientation, Data is Accessible, Data Security, Responsive Change Management

C.

Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data Security

D.

Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management

Expert Solution
Questions # 3:

Scenario:

Please read this scenario prior to answering the Question

You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.

The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.

TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario

In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.

B.

You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security

C.

You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees. You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security

D.

You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being de

Expert Solution
Questions # 4:

Chiamin Metals is a leading world-wide manufacturer for continuous casting and bottom pouring powders. In addition to mould powders, the company also produces cored wire for secondary metallurgy. Chiamin Metals offers a variety of products and uses a paper-based catalog to sponsor them. A new CIO has joint the enterprise and has set up a team of Enterprise Architects following the TOGAF 9 practice. The main challenge is now to offer to Chiamin Metals customers a centralized and reliable entry point for their request via the implementation of a global online portal. This will allow the management of new marketing activities and will enable the new Chiamin Metals' ecommerce service.

Refer to the scenario above

You are the Chief Architect and the CIO asked you to present an Architecture Vision to address the above business problem. Identify the best answer accordingly to the TOGAF 9.

Choose one of the following answers

Options:

A.

You identify key stakeholders, their concerns, and define the key business requirements to be addressed in the architecture engagement and generate a Stakeholder Map. You Evaluate business capabilities and execute a Business Transformation Readiness Assessment. You apply the Business Scenarios technique to create a high-level view of the Baseline and Target Architectures also based on the stakeholder concerns, business capability requiremen

B.

As requested by the CIO you focus on the Architecture Vision documentation and apply the Business Scenarios technique to create a high-level view of the Baseline and Target Architectures also based on the stakeholder concerns, business capability requirements, scope, constraints, and principles.

C.

You create a high-level view of the Target Architectures and then present them to the CIO.

D.

As requested by the CIO you focus on the Architecture Vision and create a detailed view of the Baseline Architectures. This is done for Business, Data, Application and Technology domains and then presented to the CIO using the Architecture Definition Document.

Expert Solution
Questions # 5:

Scenario

Please read this scenario prior to answering the question

You have been assigned the role of Lead Enterprise Architect for a firm that is a major OEM parts supplier to the auto industry. Europe has been the primary market for its products, with just 20% of its output being exported to North America. The firm is planning to expand its exports to North America and also to establish sales in South America and the Asia Pacific region. This will enable them to better ride out recessions in key markets such as Europe. It will also enable the firm to exploit the auto industry move to global platforms.

The firm is organized into business units with each addressing different auto industry sectors. Each business unit has acquired other procedures to expand its manufacturing capacity. This has resulted and manufacturing systems.

The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are joint sponsors of the EA program. The EA program is mature, with an Active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF Architecture Content Framework. The EA program is well coordinated with Project Management Office, Systems Development, and Operations functions.

The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.

A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed change and how to manage the associated risks.

Refer to the Scenario

You have been asked how to address the concerns of the CIO.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

In Phase A, the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. The matrix should include a list of factors to be considered, their descriptions, and constraints that should be taken into account. These factors can then be used to assess the initial risks associated with the proposed project.

B.

In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful reorganization. There should then be an assessment of each factor on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed project.

C.

In Phase A, the team should conduct a Business Scenario to describe the business problem, identify the stakeholders' and the resulting retirements. Once the requirements have been identified, they can be assessed in terms of their risks. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decid

D.

In Phase A, the team should evaluate the organization’s readiness to undergo change. This will identify the factors that will influence the reorganization. This should include a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed project.

Expert Solution
Questions # 6:

TP Banking is a strong financial institute with a well-known acquisition history with an internal IT department managing over 100 projects related to infrastructure and services.

The CIO has decided to create an Enterprise Architecture based on TOGAF 9 as reaction to the difficult market conditions. An Architecture Vision and a set of domain architectures were approved. The CIO is asking you (the Lead Architect) to define an Implementation and Migration Plan that realizes the vision already agreed with the stakeholders involved.

Refer to the scenario above

You are leading a group of domain architects and you are working with the corporate PMO, the business strategy team and service operations. You are meeting the stakeholders to clarify how you want to proceed with the Implementation and Migration Plan.

Choose one of the following answers

Options:

A.

You propose to start collecting the existing deliverables describing the different domains in order to enable the Enterprise Architecture tram to integrate them with the support of the operation management. Every domain architect will then evaluate the impact on the projects already planned for the domain. The single revised plans will be integrated together and consolidated into a strategic implementation and migration strategy defining an

B.

You communicate the need for urgency. The projects already planned will be cancelled and the implementation of the new architecture vision will be set as first priority. A set of new projects will be defined to implement the new strategy. You will use the requirements from Phases B through D and define new projects for each one of the requirements. The use of defined interoperability architecture guidelines will then enable the project team

C.

You describe the concept of Transition Architectures and clarify that the business value can be achieved by all the projects delivering their increments in a coordinated approach. Capability gaps and project dependencies are analyzed for each domain this will then enable the projects to be organized in work packages. You will then agree on the roadmap for the implementation and migration strategy meeting with all the key stakeholders.

D.

You communicate the CIO's will to transform the corporation and then that he's seeking help from the domain architects to do that. The requirements are managed in order to enable every Architect to participate to the planning that will result in a detailed list of work activities with impact on the IT portfolio of projects. A five year Target Architecture will then be defined and a report will keep track of dependencies and factors assessme

Expert Solution
Questions # 7:

Scenario: Zephyr Enterprises

Please read this scenario prior to answering the question

Zephyr Enterprises specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. Zephyr has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturers design specifications.

Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Zephyr has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.

Zephyr has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise Architecture to closely follow the TOGAF 9 framework. All of Zephyrs IT architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.

An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.

Refer to the Zephyr Enterprises Scenario

You are the Lead Architect for this activity.

You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization.You recommend that if a deviation from the contract is d

B.

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal envelopment projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture

C.

You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Manufacturing Architecture Board and the implementation organization.You ensure that the Manufacturing Architecture Board rev

D.

You create an Architecture Contract to govern the implementation and migration process at each site. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the contract addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management.You then schedule compliance reviews at key points in the implementation process to ensure that the work is pr

Expert Solution
Questions # 8:

Scenario

Please read this scenario prior to answering the question

You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.

The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to "leverage the synergies" that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.

The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.

TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario

In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.

Based on TOGAF, which of the following is the best answer?

Options:

A.

You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being de

B.

You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concerns in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.

C.

You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security

D.

You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees. You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security

Expert Solution
Questions # 9:

Scenario: Armstrong Defense Industries

Please read this scenario prior to answering the question

Armstrong Defense Industries is the prime contractor for the Dreadnought Unmanned Aircraft System program.

Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Armstrong Defense is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.

To achieve this goal, Armstrong Defense needs to define Baseline and Target Architectures. These architectures must address key stakeholders concerns such as:

1. What groups of people should be involved in procurement-related business processes?

2. What current applications do those groups use?

3. Which procurement-related business processes are supported by zero, one, or many existing applications?

4. What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?

5. What non-procurement applications will need to be integrated with any new procurement applications?

6. What data will need to be shared?

At present, there are no particularly useful architectural assets related to this initiative. All assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.

The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.

Armstrong Defense is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.

Refer to the Armstrong Defense Industries Scenario

You are serving as the Lead Architect.

You have been asked to identify the most appropriate architecture viewpoints for this situation.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

In the early iterations of the Architecture Definition: • Describe the Baseline Business Architecture with a Baseline Business Process catalog• Describe the Baseline Application Architecture with a Technology Portfolio catalog• Describe the Baseline Data Architecture with a Data diagramIn the later iterations of the Architecture Definition: • Describe the Target Business Architecture with an Actor/Process/Data catalog• Describe the Target A

B.

In the early iterations of the Architecture Definition: • Describe the Target Business Architecture with a Business Service/Function catalog and a Business Interaction matrix• Describe the key business objects with Product Lifecycle diagrams• Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix• Describe the Target Data Architecture with a Data Entity/Business Function ma

C.

In the early iterations of the Architecture Definition: • Describe the Target Business Architecture with a Business Service/Function catalog and an Organization/Actor catalog• Describe the key business objects with Data Lifecycle diagrams• Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix• Describe the Target Data Architecture with a System/Data matrixIn the later iter

D.

In the early iterations of the Architecture Definition: • Describe the Baseline Business Architecture with an Organization/Actor catalog• Describe the Baseline Application Architecture with a System/Function matrix• Describe the Baseline Data Architecture using a Data Entity/Data Component catalogIn the later iterations of the Architecture Definition: • Describe the Target Business Architecture with en Organization/Actor catalog• Describe t

Expert Solution
Questions # 10:

Patterns & Co. is introducing a Commercial Off-the-Shelf (COTS) Market Analytics solution in order to improve its new delivery service.

Patterns & Co. has a mature enterprise architecture capability and the CIO is the sponsor of the enterprise architecture team. The business vision and requirements for the new system are defined. It includes a detailed business process analysis. The supplier has proposed a solution but the Architecture Board identified some of the project requirements not consistent with the adopted infrastructure standards. The CIO considered the risks and approved the implementation.

The CIO has asked the EA team to execute the Phase G ensuring that the system performance KPIs are respected, the project remains within budget and security guidelines are met.

Refer to the scenario above

As Lead Enterprise Architect you have to recommend a plan to implement the CIO decision. Choose the best answer according to TOGAF 9.

Choose one of the following answers

Options:

A.

You ask the supplier to modify the web server hardware and software components so they can meet the current infrastructure standards. You advise to execute a proof of concept to anticipate any coding issue. Then, after the agreement with the development leads for supporting the development, you will provide the project plan to the project manager and develop an Architecture Contract. A set of frequent operational reviews to monitor the solu

B.

You recommend the co-existence of a second web server standard and modify the company Standards Information Base adding this new technology.You ask the project architects to create an Architecture Contract with the development teams. You identify the need of a performance testing and a compliance review You agree with the business on SLA and delivery dates. You identify re-usable procedures and objects.

C.

You eliminate the non-standard web server from the solution as recommended by the Architecture Board. You create a revised plan and Architecture Contract for the development stressing the re-use of standard technologies. You share the budget implication of this solution with a finance committee and inform the CIO of the long term cost benefits of this choice. You define periodical project management meetings to monitor compliance.

D.

You execute a risk analysis and set deliverables and timing requirements with the development team. You implement a detailed impact analysis of the chosen solution. You create an Architecture Contract and ask for the CIO's approval before implementing it. You test the solution just prior to implementation and deliver the project artifacts and store after the completion of the implementation.

Expert Solution