Questions # 11:

RIG Networks, a global network supplier is implementing a massive replacement of its supply chain to reduce production cost of their new LTE (Long Term Evolution) gateways. As part of this renovation process the CIO decided to replace their ERP (Enterprise Resource Planning) system using a greenfield approach (where the legacy ERP system will be decommissioned). The CIO engaged a team of TOGAF 9 certified consultants to design the solution, he then identified the suppliers and asked you as Chief Architect to supervise the definition of the Architecture Design and Development Contract.

Refer to the scenario above

You now need to write the Architecture Design and Development Contract, identify how you would o this following TOGAF 9.

Choose one of the following answers

Options:

A.

You would define the Architecture Design and Development Contract with : introduction and background, the nature of the agreement, scope of the architecture, architecture and strategic principles and requirements, conformance requirements, Target Architecture Measures, Define phases of deliverables, Prioritized joint workplan, Time window, Architecture delivery and business metrics.

B.

You would define the Architecture Design and Development Contract with : introduction and background, the nature of the agreement, scope of the architecture, architecture and strategic principles and requirements, conformance requirements, Baseline Architecture definition, Target Architecture Measures, Define phases of deliverables, Prioritized joint workplan, Time window, Architecture delivery and business metrics.

C.

You would define the Architecture Design and Development Contract with : Target Architecture Measures, Define phases of deliverables, Prioritized joint workplan, Time window, Architecture delivery and business metrics.

D.

You would define the Architecture Design and Development Contract with : scope, goals, objectives and constraints, Architecture Principles, Baseline Architecture, Architecture Models, Gap Analysis, Impact Assessment.

Expert Solution
Questions # 12:

Scenario

Please read this scenario prior to answering the question

You are serving as the Lead Architect for the Enterprise Architecture team at a multinational company. The company has grown rapidly by acquisition and has inherited numerous supply chain processes and related IT systems. Several supply chain processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant processes and systems. The company will move to a "Just-in-time" supply chain management so as to keep inventory costs low.

The TOGAF standard is followed for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).

At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing supply chain management processes or systems.

The architecture development project has completed Phase A and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:

1. What groups of people should be involved in the supply chain management-related business processes?

2. What non-supply chain management applications will need to be integrated with any new supply chain management applications?

3. What data will need to be shared?

Refer to the Scenario

[Note: You may need to refer to the Architectural Artifacts chapter, section 31.6 (located in Part IV) of the reference text in order to answer this question.]

You have been asked to identify the most appropriate catalogs matrices and diagrams to support the next iteration of Architecture development.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

You would describe the Baseline Business Architecture with a Business Service/function catalog, an Organization/Actor catalog, and a Data Entity/Business Function matrix. You would describe the Baseline Data Architecture using a Data Entity/Data Component catalog. You would describe the Baseline Application Architecture with an Application/Function matrix.

B.

In the next iteration of Architecture development, you would describe the Target Business Architecture with an Organization/Actor catalog, a Business Service/Function catalog, and Data Lifecycle diagrams. You would describe the Target Application Architecture with a Data Entity/Data Component catalog. You would describe the Target Application Architecture with an Application Interaction matrix and Application Communication diagrams.

C.

You would describe the Target Business Architecture with a Business Service/Function catalog, and a Business Interaction matrix. You would describe the Target Data Architecture with a Data Entity/Business Function matrix and an Application/Data matrix. You would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix.

D.

In the next iteration of Architecture development, you would describe the Baseline Business Architecture with a Value Chain diagram, and a Baseline Business Process catalog. You would describe the Baseline Data Architecture with a Data diagram. You would describe the Baseline Application Architecture with an Environments and Locations diagram.

Expert Solution
Questions # 13:

Please read this scenario prior to answering the question

Worldwide Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.

Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new finding about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. WorldwideMobile actually has better coverage in nearly all markets than Air Light, and good roaming agreement that keep rates low for business travellers. But customer satisfaction has remained low.

The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.

The planning for the program has been underway for several months. WorldwideMobile has selected TOGAF 9 as the basis for its Enterprise Architecture.

The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Executive Council has stated that the program should define specific initiatives to enable each regional business units to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.

Refer to WorldwideMobile-2 Scenario

You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.

The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At present time, the project team is conducting an architecture development project that is focused on the customer self service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.

The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability.

You have been asked to recommend the course of action to complete the project.

Based on TOGAF 9, which of the following is best answer?

Options:

A.

In the remaining architecture definition phases, the project team should map out the capability in the Technology domain. In the Phases E and F, the capability should be broken down into a set of Solution Building Blocks that define the Target Architecture. Where possible, the Solution Building Blocks should be drawn from the Architecture Repository. The completed Architecture Definition Document and the Implementation and Migration Plan wi

B.

In the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that are sequenced into Transition Architectures that will lead to the realization of the Target Architecture. The resulting Solution Building Blocks will then provide the basis for the capability in

C.

In the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that defines the Target Architecture. The Solution Building Blocks will provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation

D.

The remaining architecture definition work should be focused on mapping out the technology and infrastructure capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that will be implemented to realize the Target Architecture. The Solution Building Blocks will provide the basis for the completed Architecture Definition Document that will be submitted for approval. U

Expert Solution
Questions # 14:

Please read this scenario prior to answering the question

You are serving as the Lead Architect for a chain of convenience stores, operating as a franchise, which has over 5000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and rely on point-of-sale technology to manage their inventory.

Stores place all orders on-line. The back-office systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible.

An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better accommodate the changing strategies within the company and also better respond to changes in economic and technical environments.

The CIO has stated that the following issues need to be addressed in the restructuring:

The systems should be able to withstand any unforeseen disruptions which might affect day to day operations. This is highly critical for ensuring high levels of customer satisfaction and maintaining and growing revenue.

Dependencies between the application components, the application platform, and technology infrastructure should be minimal and well defined. This will facilitate scalability and ease of enhancement of the service offerings.

The company is adopting the ARTS Operational Data Model and Data Warehouse Model from the National Retail Federation. This will address past problems with data quality and inconsistent data.

To remain competitive, new products and promotions must undergo market trials and if these are successful, deployed across the retail chain. Information systems must be able to manage changes and updates without undue delays.

Refer to the Scenario

[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.]

You have been asked to identify the most relevant architecture principles for the current situation.

Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]

Options:

A.

Interoperability, Data is Accessible, Data is Shared, Requirements Based Change, Control Technical Diversity

B.

Technology Independence, Business Continuity, Common Vocabulary and Data Definitions, Data Trustee, Responsive Change Management

C.

IT Responsibility, Data Security, Ease of Use, Requirements Based Change, Common Use Applications

D.

Interoperability, Maximize Benefit to the Enterprise, Data Trustee, Data is an Asset, Responsive Change Management

Expert Solution
Questions # 15:

ARTI Dimensioning is a multinational that operates production facilities in 29 countries and sells its products in over 120 countries.

A consultancy firm has recommended a realignment that will enhance sharing of product information across business units. The implementation of this strategic realignment will require the development of integrated customer information systems and product information systems.

ARTI has a mature enterprise architecture practice and uses TOGAF 9 for the basis of the ARTI Architecture Framework (method and deliverables). The CIO is sponsoring an architecture development program that is going to start. The CIO is concerned about a potential disruptive result to the business of this activity and before proceeding with the architecture development he asked to evaluate the impacts on the company business.

Refer to the scenario above

You are the Lead Architect and you have been asked to recommend an approach to address the concerns raised. Based on TOGAF 9 recommend which of the following is the best answer.

Choose one of the following answers A.

A Risk Aversion Assessment should be conducted during the Implementation Governance phase to determine the degree of risk aversion of the proposed business transformation. After sharing the residual level of risk with the company chairman and the residual risk is not accepted, a set of parallel systems will be implemented to mitigate the risks.

B. Your recommendation is to use risk management techniques to assess the risks associated with the proposed business transformation and ensure the existence of business continuity plans. During the Implementation Governance phase you conduct a residual risk assessment to manage risks that cannot be mitigated.

C. During the Architecture Vision phase a risk assessment is conducted to mitigate initial risks and address those in the Architecture Contract signed in the Implementation Governance phase.

D. Your proposal is to utilize a risk management framework during the Implementation Governance phase to verify the risks associated with the proposed transformation of the business. You then share with the concerned stakeholders the residual level on risk before the Architecture Contracts are released.

Options:

Expert Solution
Questions # 16:

Please read this scenario prior to answering the question

You are serving as the Lead Architect for a chain of convenience stores, which has over 2000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and use the latest cloud-based point-of-sale (POS) technology to manage their sales and inventory. Cloud-based POS systems store all user data, including sales and inventory in a remote server.

The cloud-based systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day’s weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible. The stores also act as self-service delivery locations for a large online retailer which further increases the number of potential customers entering the stores.

An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better support the existing environment and accommodate future changes of strategy within the company.

The CIO has stated that the following issues also need to be addressed in the restructuring:

- They need to address problems with data quality and inconsistent data in order to support better decision making and analysis.

- The architecture should focus on the needs of the business, not technology.

- To remain competitive, new products and promotions must undergo market trials before deployment across the retail chain. Information systems must be able to manage changes and updates without undue delays.

Refer to the Scenario

[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.]

You have been asked to identify the most relevant architecture principles for the current situation.

Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]

Options:

A.

Maximize Benefit to the Enterprise, Data Trustee, Data is an Asset, Responsive Change Management, Interoperability.

B.

Requirements Based Change, Responsive Change Management, Data Trustee, Common Vocabulary and Data Definitions, Business Continuity.

C.

IT Responsibility, Data security, Ease of Use, Service Orientation, Common Use Applications.

D.

Data is Accessible, Data is shared, Interoperability, Requirements Based Change, Control Technical Diversity.

Expert Solution
Questions # 17:

FreshFruit Int. is an online American grocer. The Executive Board decided to implement a new strategy to expand the business to other markets.

The CIO is sponsoring an enterprise activity to support the expanded operations.

A new solution is rolled-out to replace the legacy online sales platform. A compliance review was performed to assess the solution implementation.

The result of the review highlighted a complaint from the development team stating that the new system is difficult to integrate with the existing warehouse automation systems. The Chief Architect is concerned that the complaint is not related to a real problem of the solution but is based on personal preferences of the development teams. Another interview with the project team is scheduled.

Refer to the scenario above

You are the Lead Architect and an architect from your team leads the review team. You have to answer how, based on TOGAF 9, you should enable the review team to conduct the reviews successfully.

Choose one of the following answers

Options:

A.

Meeting with the project architect you clarify the purpose of the review. You ask to perform an objective and fair review using the checklists to frame the review and clarify that you want them to identify the issues behind the implementation team complaints.

B.

You organize a meeting with the review team and state the importance to identify any non-compliancy that may have come from the implemented solution.

C.

You organize a meeting with the review team and stress the importance of a high degree of compliance without any exception. The review should cover every aspect of the implementation and should criticize the implementation techniques.

D.

You verify that criteria for the program and the business objectives are mapped in the checklists that the project team prepared for the interviews. You confirm the checklist content to the project architect and stress the need to be objective and fair during the review process.

Expert Solution
Questions # 18:

Scenario: Marona Inc.

Marona Inc is a Fortune 500 Enterprise in the retail industry with retail store components manufacturing units and marketing outlets spanning the globe and having an annual turnover of 20 billion$ with more than 100, 000 employees world wide.

The CEO, CIO and the stakeholders of the ongoing EA projects are concerned about rising costs and as one measure want to do an investigation into the operational aspects of the realized Enterprise Architecture using TOGAF9.

The CIO approaches you as the Lead Enterprise Architect to carry out this exercise the stakeholder had voiced to him the following concerns:

They want to analyze the roles of the top management for each revenue earning service. Moreover, many of the HR related critical Search application component have become extremely slow. This needs to be diagnosed and rectified. Moreover there is no proper tracking of revenue from retail store component products over time. There has also been a lot of unauthorized or unwanted access to many of the critical information.

Hence the mode of access needs to be strengthened and made much more secure. Another additional concern is the new launches and the progress of each of the launches over time.

Determine which of the following set of viewpoints are most appropriate to analyze and view in order to address this concern of the stakeholders.

Options:

A.

(i) System/Functions Matrix(ii) Actor/Role Matrix(iii) Data Entity/Business Function Matrix(iv) Technology Portfolio Catalog(v) Data Security Diagram

B.

(i) Goal/Objective/Service Diagram(ii) Contract Measure Catalog(iii) Data Dissemination Diagram(iv) Application Communication Diagram(v) Data Life Cycle Diagram

C.

(i) Location Catalog(ii) Service/Function Catalog(iii) Data Entity/Business Function Matrix(iv) Application Communication Diagram

D.

(i) System/Functions Catalog(ii) System/Technology Matrix(iii) Goal/Objective/Service Diagram(iv) Product Life Cycle Diagram(v) Data Security Diagram

Expert Solution
Questions # 19:

Carter Woods, a global furniture firm, wants to improve the efficiency of its sales force by replacing their legacy configuration and ordering systems based on manual and paper based processes with an online ordering platform.

Carter Woods uses the Architecture Delivery Method from TOGAF 9. The CIO sponsored this activity and the Baseline Architecture was defined on the initial iteration defining: approach, scope and architectural vision including a set of architecture principles related to the Data domain:

Data is an asset.

Data is shared.

Data is accessible.

A set of aspects to clarify arose from the business analysis from the assumption to replace the legacy systems with an online centralized one. These main concerns are:

· To identify the changes to existing business processes.

· To identify the data entities that can be shared among the sales agents.

· To clarify how to keep the data secured.

· To identify the list of non-sales application to be integrated with the sales applications

Refer to the scenario above

You, as Lead Enterprise Architect, need to identify the most appropriate architecture viewpoints to address the concerns above mentioned.

Choose one of the following answers

Options:

A.

Depict the Business Architecture using a Role catalog and a Process/Event/Control/Product catalog. Depict the Data Architecture using a System/Data matrix, a Data Entity/Data Component catalog and Data Security diagram. Depict the Application Architecture using an Interface catalog. Define the Technology Architecture via a Network Computing/Hardware diagram.

B.

Depict the Business Architecture using a Business Interaction matrix and a Location catalog. Depict the Data Architecture using a Data Lifecycle diagram and a Data Migration diagram. Depict the Application Architecture using a Software Engineering diagram. Depict the Technology Architecture using a Communications Engineering diagram.

C.

Depict the Business Architecture using a Business Footprint diagram and a Location catalog. Depict the Data Architecture using a Data Migration diagram, System/Data matrix and Data Lifecycle diagram. Depict the Application Architecture using an Application Communication diagram. Depict the Technology Architecture using a Network Computing/Hardware diagram.

D.

Depict the Business Architecture using a Role catalog and Location catalog. Depict the Data Architecture using a System/Data matrix, Data Entity/Business Function matrix and Data Security diagram. Depict the Application Architecture using an Application Interaction matrix. Define the Technology Architecture via a Network Computing/Hardware diagram.

Expert Solution
Questions # 20:

Scenario

Please read this scenario prior to answering the question

Your role is consultant to the Lead Architect within a multinational semiconductor and software design company. Its largest business is in processors, although it also designs system-on-a-chip infrastructure and manufactures memory chips. A characteristic feature of its processors is their low electric power consumption, which makes them particularly suitable for use in portable devices. As well as licensing its technology, the company has several manufacturing divisions.

The company has a mature enterprise architecture practice and uses TOGAF Standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.

The company has defined a strategic architecture to improve its ability to meet customer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.

Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.

The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment. They have also completed the Implementation and Migration Plan v0.1, the draft Architecture Roadmap, and the Capability Assessment deliverables.

Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.

Refer to the Scenario

You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.

Based on TOGAF Standard Version 9.2, which of the following is the best answer?

Options:

A.

You recommend that the enterprise architects apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. They should confirm the Transition Architecture phases using an Architecture Definition Increments Table to list tine proj

B.

You recommend that the enterprise architects conduct a series of Compliance Assessments to ensure that the architecture is being implemented according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements

C.

You recommend that the enterprise architects assess how the plan impacts the other frameworks in use in the organization. Minimally, the plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. They should then assign a business value to each project, taking into account available resources and priorities for the projects. Finally, they should generate the Implementation and M

D.

You recommend that the enterprise architects place the Architecture Definition Document under configuration control. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. They should then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be applied as changes to the architecture without review.