Questions # 41:

Under which of the following scenarios an RFQ is most likely to be used?

Options:

A.

Purchase of a small number of standardised products under a framework agreement

B.

Purchase of complex machinery

C.

Design of a unique and complex software code

D.

When the buying organisation does not know the requirements in details and needs the input from suppliers

Questions # 42:

Electro Systems PLC is a public sector manufacturer of highly technical solutions for the telecommunications industry. The market in which it operates is fast-paced and ever-changing because of the latest inventions and developments. The products it procures are high-cost and can be subject to lengthy lead times. Michael Jones, the procurement director, believes that establishing framework agreements would be beneficial to the tendering process. How could this assist them?

Options:

A.

Improve supplier lead times

B.

Enable the use of mini-competitions

C.

Improve supplier product quality

D.

Enable the use of e-tendering

Questions # 43:

Maximum Score 1

Which of the following would you expect to see in an Invitation to Tender (ITT)?

Options:

A.

Best and Final Offer (BAFO)

B.

Supplier rates

C.

Liquidity ratios

D.

Delivery milestones

Questions # 44:

A service contract is going to be expired, which data source is good to create specifications for ITT?

1. Incumbent supplier

2. Maintenance services

3. Alternative supplier

4. User's knowledge

Options:

A.

1, 2 and 3

B.

1, 3 and 4

C.

1, 2 and 4

D.

2, 3 and 4

Questions # 45:

To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity and risks of such project. Hugo, the procurement manager, suggests that the company can adopt a model form of contract. What is the advantage of using model form of contract?

Options:

A.

It shifts the balance of power in the favour of the buyer rather than the contractor

B.

The company could avoid the need to draft a complex contract from blank

C.

Model form of contract eliminates the need for legal advice totally

D.

The company does not need to draft the drawings as well as specification anymore

Questions # 46:

Which of the following would be suitable key performance indicators (KPIs) for supplier performance?

Ensure you have customer loyalty

Value or percentage of cost reductions obtained

Win an award in the next 12 months

Percentage of on-time in full deliveries

Options:

A.

1 and 3 only

B.

2 and 4 only

C.

1 and 4 only

D.

2 and 3 only

Questions # 47:

Which of the following is the international standard for labelling hazardous substances?

Options:

A.

GPS

B.

HSE

C.

CODEX STAN 1-1985

D.

GHS

Questions # 48:

Which of the following contracts would be best suited to a ‘variable pricing’ arrangement?

Options:

A.

A contract for window cleaning during the next three months

B.

A contract for road building estimated to take five years to complete

C.

A contract for the supply of 100 printing machines to be delivered next month

D.

A contract for the supply of lubricating oil for immediate delivery

Questions # 49:

An organization has a normal tender process that often last 1 month from defining the needs to contract award. Manufacturing department suddenly required a new special part that they could not foresee within a month. Which of the following should be the priority actions of procurement manager in this urgent situation? Select TWO that apply:

Options:

A.

Design new specification

B.

Develop relationships with potential suppliers

C.

Review contract performance

D.

Get high-level authority approval

E.

Submit full business justification

Questions # 50:

Prior to circulating the service specification to a tendering supplier, it is good practice for the purchasing organisation to request completion of a non-disclosure agreement. Is this statement correct?

Options:

A.

No, because the non-disclosure agreement has no legal standing

B.

Yes, because the non-disclosure agreement protects intellectual property

C.

Yes, because the non-disclosure agreement encourages transparent bidding

D.

No, because the non-disclosure agreement only applies after contracting

Viewing page 5 out of 7 pages