Questions # 151:

Which of the following is the BEST indicator of a successful project?

Options:

A.

it is completed on time or early as compared to the baseline project plan

B.

it meets most of the specifications as outlined in the approved project definition

C.

it comes in at or below the expenditures planned for in the baseline budget

D.

the deliverables are accepted by the key stakeholders

Expert Solution
Questions # 152:

Which of the following functions evaluates risk present in IT initiatives and/or systems when implementing an information security program?

Options:

A.

Risk Management

B.

Risk Assessment

C.

System Testing

D.

Vulnerability Assessment

Expert Solution
Questions # 153:

Which of the following is the MOST important component of any change management process?

Options:

A.

Scheduling

B.

Back-out procedures

C.

Outage planning

D.

Management approval

Expert Solution
Questions # 154:

A CISO decides to analyze the IT infrastructure to ensure security solutions adhere to the concepts of how hardware and software is implemented and managed within the organization. Which of the following principles does this best demonstrate?

Options:

A.

Alignment with the business

B.

Effective use of existing technologies

C.

Leveraging existing implementations

D.

Proper budget management

Expert Solution
Questions # 155:

The company decides to release the application without remediating the high-risk vulnerabilities. Which of the following is the MOST likely reason for the company to release the application?

Options:

A.

The company lacks a risk management process

B.

The company does not believe the security vulnerabilities to be real

C.

The company has a high risk tolerance

D.

The company lacks the tools to perform a vulnerability assessment

Expert Solution
Questions # 156:

Risk appetite is typically determined by which of the following organizational functions?

Options:

A.

Security

B.

Business units

C.

Board of Directors

D.

Audit and compliance

Expert Solution
Questions # 157:

In order for a CISO to have true situational awareness there is a need to deploy technology that can give a real-time view of security events across the enterprise. Which tool selection represents the BEST choice to achieve situational awareness?

Options:

A.

Vmware, router, switch, firewall, syslog, vulnerability management system (VMS)

B.

Intrusion Detection System (IDS), firewall, switch, syslog

C.

Security Incident Event Management (SIEM), IDS, router, syslog

D.

SIEM, IDS, firewall, VMS

Expert Solution
Questions # 158:

The ultimate goal of an IT security projects is:

Options:

A.

Increase stock value

B.

Complete security

C.

Support business requirements

D.

Implement information security policies

Expert Solution
Questions # 159:

Knowing the potential financial loss an organization is willing to suffer if a system fails is a determination of which of the following?

Options:

A.

Cost benefit

B.

Risk appetite

C.

Business continuity

D.

Likelihood of impact

Expert Solution
Questions # 160:

When entering into a third party vendor agreement for security services, at what point in the process is it BEST to understand and validate the security posture and compliance level of the vendor?

Options:

A.

At the time the security services are being performed and the vendor needs access to the network

B.

Once the agreement has been signed and the security vendor states that they will need access to the network

C.

Once the vendor is on premise and before they perform security services

D.

Prior to signing the agreement and before any security services are being performed

Expert Solution
Questions # 161:

When operating under severe budget constraints a CISO will have to be creative to maintain a strong security organization. Which example below is the MOST creative way to maintain a strong security posture during these difficult times?

Options:

A.

Download open source security tools and deploy them on your production network

B.

Download trial versions of commercially available security tools and deploy on your production network

C.

Download open source security tools from a trusted site, test, and then deploy on production network

D.

Download security tools from a trusted source and deploy to production network

Expert Solution
Questions # 162:

Which of the following is considered one of the most frequent failures in project management?

Options:

A.

Overly restrictive management

B.

Excessive personnel on project

C.

Failure to meet project deadlines

D.

Insufficient resources

Expert Solution
Questions # 163:

Which of the following is MOST beneficial in determining an appropriate balance between uncontrolled innovation and excessive caution in an organization?

Options:

A.

Define the risk appetite

B.

Determine budget constraints

C.

Review project charters

D.

Collaborate security projects

Expert Solution
Questions # 164:

An organization has a stated requirement to block certain traffic on networks. The implementation of controls will disrupt a manufacturing process and cause unacceptable delays, resulting in sever revenue disruptions. Which of the following is MOST likely to be responsible for accepting the risk until mitigating controls can be implemented?

Options:

A.

The CISO

B.

Audit and Compliance

C.

The CFO

D.

The business owner

Expert Solution
Questions # 165:

Which of the following are not stakeholders of IT security projects?

Options:

A.

Board of directors

B.

Third party vendors

C.

CISO

D.

Help Desk

Expert Solution