Questions # 81:

Which from the following list are typically found to enable the review process to be successful? [K2]

a. Each review has clear defined objectives

b. The lower the number of defects, the better the review process

c. The right people for the review objective are involved

d. There is an emphasis on learning and process improvement

e. Management are not involved in the process at all

f. Checklists should not be used, as these slow down the process

g. Defects found are welcomed and expressed objectively

Options:

A.

a, f and g.

B.

b, c and f.

C.

a, c and d.

D.

d, e and g.

Expert Solution