Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the PMI PMI-RMP Questions and answers with ValidTests

Exam PMI-RMP All Questions
Exam PMI-RMP Premium Access

View all detail and faqs for the PMI-RMP exam

Viewing page 8 out of 9 pages
Viewing questions 71-80 out of questions
Questions # 71:

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.  

Expert Solution
Questions # 72:

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Expert Solution
Questions # 73:

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.

Monte Carlo analysis

B.

Update risk register

C.

Brainstorming

D.

Cost and time estimating

Expert Solution
Questions # 74:

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Expert Solution
Questions # 75:

A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.

What should the risk manager do?

Options:

A.

Focus on high-probability concerns first to proactively address the most immediate threats.

B.

Delegate the assessment of lower-priority concerns to team leads while addressing critical ones.

C.

Evaluate all identified concerns and consider likelihood and impact to prioritize the concerns effectively.

D.

Prioritize uncertainties that align closely with the project's primary deliverables.

Expert Solution
Questions # 76:

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

B.

Regularly check and report on the status of risks identified according to their prioritization.

C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Expert Solution
Questions # 77:

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project

B.

By helping to determine the overall project risks

C.

By helping the lessons learned from previous risks to be efficiently utilized

D.

By helping to update the project scope statement document

E.

By helping update the risk register and close out expired risks 

Expert Solution
Questions # 78:

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

Options:

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

Expert Solution
Questions # 79:

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Expert Solution
Questions # 80:

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Options:

A.

Request a contingency reserve from management

B.

Arrange a team meeting, review the project ' s scope, and discuss dependency mapping

C.

Ensure participants review relevant documents before attending the meeting

D.

Ensure that all the relevant stakeholders participate

E.

Update the risk register during the team meeting.

Viewing page 8 out of 9 pages
Viewing questions 71-80 out of questions