Questions # 21:

What can a Scrum Master/Team Coach recommend to a team that is showing signs of burnout, not addressing increasing technical debt, and acting out of urgency rather than considering innovation?

Options:

A.

A constructive IP Iteration at the end of each PI

B.

A collective Iteration Review and demo each Iteration

C.

A communicative retrospective at the end of each Iteration

D.

A careful plan at the beginning of each Iteration

Expert Solution
Questions # 22:

What is the intended value of the Backlog Refinement event?

Options:

A.

The team is able to prepare requirements for Iteration Planning

B.

The team aligns on the progress of Iteration Goals

C.

The team is able to commit to a set of goals to be delivered in the Iteration

D.

The team reviews and improves processes before the next Iteration

Expert Solution
Questions # 23:

What is one potential root cause of Team Sync anti-patterns?

Options:

A.

Overcommunication between team members

B.

Lack of collective ownership

C.

Occasional conflict within the team

D.

Frequent verification and integration during the Iteration

Expert Solution
Questions # 24:

What is one SAFe recommended practice Scrum Masters/Team Coaches can use to track Iteration progress?

Options:

A.

Combine multiple stories into larger stories

B.

Push defects to the Innovation and Planning (IP) Iteration

C.

Facilitate backlog refinement of the current iteration

D.

Communicate potential missed goals or objectives as early as possible

Expert Solution
Questions # 25:

How can teams use Iteration planning to stay aligned on their work?

Options:

A.

By reviewing its processes before the next iteration

B.

By committing to a set of goals to be delivered

C.

By agreeing on a meeting timebox

D.

By sharing Stories that could be pairing opportunities

Questions # 26:

What is one method a Scrum Master/Team Coach can use to help teams overcome a fear of conflict?

Options:

A.

Enforcing work-in-process limits

B.

Giving every team member the opportunity to contribute

C.

Scheduling regular Team Syncs

D.

Aligning to shared commitments

Questions # 27:

Which of the following statements is true about the team backlog?

Options:

A.

The team backlog is where Stories are accepted

B.

The team backlog is where the team finalizes work

C.

The team backlog is where the team refines possible Stories

D.

The team backlog is where the team commits to work

Questions # 28:

What is one way a servant leader can support team members in decision-making?

Options:

A.

Give each team member the opportunity to contribute

B.

Perform regular retrospectives on behalf of the team

C.

Identify solutions to problems the team surfaces

D.

Support teams in affinity mapping their concerns

Questions # 29:

What is the first step of the problem-solving workshop?

Options:

A.

Perform a root-cause analysis

B.

Agree on the problem to solve

C.

Restate the new problem for the biggest root cause

D.

Identify the biggest root cause

Questions # 30:

What is one element on the Scrum Master/Team Coach responsibility wheel?

Options:

A.

Facilitate Coach Sync

B.

Facilitate PI Planning

C.

Facilitate a Community of Practice

D.

Facilitate an Agile Team charter workshop