Questions # 11:

Which of the following is NOT a flow metric?

(choose the best answer)

Options:

A.

Cycle Time.

B.

Work in Progress (WIP).

C.

Throughput.

D.

Work item age.

E.

All of the above are flow metrics.

Expert Solution
Questions # 12:

True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull

system.

Options:

A.

True

B.

False

Expert Solution
Questions # 13:

How do Work in Progress (WIP) Limits relate to self-management?

(choose the best two answers)

Options:

A.

WIP Limits inhibit self-management since they limit the team's autonomy to pull

work.

B.

WIP Limits provide a boundary/container in which the Scrum Team self-

manages.

C.

A Scrum Master defines a WIP Limit to help the Scrum Team self-manage.

D.

As part of self-managing, Scrum Teams figure out their own WIP Limits.

Expert Solution
Questions # 14:

A Service Level Expectation (SLE) consists of which two items?

(Choose the best two answers)

Options:

A.

A period of elapsed days.

B.

A cost of delay.

C.

A probability.

D.

A forecasted date.

Expert Solution
Questions # 15:

A service level expectation (SLE) consists of which two items?

(choose the best two answers)

Options:

A.

A cost of delay.

B.

A probability.

C.

A forecasted date.

D.

A period of elapsed days.

Expert Solution
Questions # 16:

A Scrum Team's Definition of Workflow must have defined points at which the Scrum Team

considers work to have started and to have finished. This allows the team to track their Work in

Progress (WIP). How are these points defined?

(choose the best answer)

Options:

A.

Any refined Product Backlog item in the Product Backlog is WIP.

B.

How it is defined and who within the Scrum Team defines it depends on the

boundaries and scope of the Definition of Workflow.

C.

Any Product Backlog item in the Sprint Backlog is a WIP.

D.

In any way the Scrum Team chooses to define it. They have the final say on the Sprint Backlog.

Expert Solution
Questions # 17:

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to

observe?

(choose the best three answers)

Options:

A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Self-management would be strengthened as a result of increased transparency.

D.

Increased collaboration/swarming between the Developers.

Expert Solution
Questions # 18:

Which of the following is NOT an essential component to initially achieving flow?

(choose the best answer)

Options:

A.

Ensuring the Product Backlog is refined frequently.

B.

Limiting Work in Progress (WIP).

C.

Visualizing your Workflow.

D.

Actively managing WIP.

E.

Inspecting & adapting your Workflow.

Expert Solution
Questions # 19:

Which of the following statements about supplementing Scrum with Kanban practices is true?

(choose the best answer)

Options:

A.

Scrum Teams may choose to skip the Sprint Planning event.

B.

It encourages team collaboration/swarming.

C.

It applies primarily to maintenance type of work.

D.

It implies that the Scrum Team must have a sequential approach to work.

Expert Solution
Questions # 20:

Which of the following are flow metrics needed when doing Scrum with Kanban?

(choose the best four answers)

Options:

A.

Throughput.

B.

Lead Time.

C.

Cycle Time.

D.

Work in Progress (WIP)

E.

Work Item Age

F.

CFD

Expert Solution