Questions # 51:

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

Options:

A.

The Scrum Team includes not only developers but also business analysts, architects,

and testers.

B.

The Scrum Team includes skilled individuals who together have all the skills

necessary to create value each Sprint.

C.

Developers on the Scrum Team work closely with business analysts, architects,

developers, and testers who are not on the team.

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts,

architects, developers, and testers.

Expert Solution
Questions # 52:

True or False: Product Owners must specify complete acceptance criteria for a Product

Backlog item before the Developers can select the item in Sprint Planning.

Options:

A.

True

B.

False

Expert Solution
Questions # 53:

Which metrics will help a Product Owner determine if a product is delivering value?

(choose the best two answers)

Options:

A.

Customer satisfaction.

B.

Productivity.

C.

Velocity.

D.

Time to market.

E.

Percentage of scope implemented.

Questions # 54:

How is management that is external to the Scrum Team involved in the Daily Scrum?

(choose the best answer)

Options:

A.

The Product Owner represents their opinions.

B.

The Scrum Master speaks on their behalf.

C.

Managers are not required at the Daily Scrum.

D.

Management gives an update at the start of each Daily Scrum.

Questions # 55:

What activities would a Product Owner typically undertake in the period between the end of the

current Sprint and the start of the next Sprint?

(choose the best answer)

Options:

A.

There are no such activities. The next Sprint starts immediately after the currentSprint.

B.

Refine the Product Backlog.

C.

Update the project plan with stakeholders.

D.

Work with the Quality Assurance departments on the Increment of the current Sprint.

Questions # 56:

Which of the following practices might help the Product Owner minimize waste in developing

and sustaining the Product Backlog?

(choose the best two answers)

Options:

A.

Avoid distracting the Scrum Team by maintaining newly gathered ProductBacklog items in a separate Product Backlog until they are fully understood.

B.

Hand off ownership of the Product Backlog to someone else.

C.

Remove items from the Product Backlog that have not been addressed in a longtime.

D.

Only fully describe Product Backlog items when it seems likely they will beimplemented.

Questions # 57:

If Product Backlog refinement is needed, when is the ideal time for refinement to take place and

who should participate?

(choose the best two answers)

Options:

A.

The Scrum Team during the current Sprint, if they have been unable duringpreceding Sprints to define Product Backlog items with enough precision tobegin work.

B.

Business analysts in the organization should do this work for the Scrum Team 1- 2 Sprints ahead of the development Sprints.

C.

The Product Owner must do this as essential work in Sprint O.

D.

The Product Owner takes the time between the end of one Sprint and the startof the next Sprint to complete refinement.

E.

The Scrum Team on an ongoing basis, defining Product Backlog items intosmaller more precise items that are ready for selection.

Questions # 58:

Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

(choose the best answer)

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Scrum Team.

E.

All of the above.

Questions # 59:

True or False: An Increment must be released to customers or users at the end of each Sprint.

Options:

A.

True

B.

False

Questions # 60:

What is the timebox for the Sprint Review?

(choose the best answer)

Options:

A.

2 hours for a one-month Sprint.

B.

1 day.

C.

4 hours for a one-month Sprint.

D.

As long as needed.