Which statement best describes the Sprint Backlog as the output of the Sprint Planning?
(choose the best answer)
What are two effective ways for the Scrum Team to make non-functional requirements visible?
(choose the best two answers)
True or False: A Product Owner with multiple teams working on one product should maintain
separate Product Backlogs for each team.
What three things might a Scrum Product Owner focus on to ensure the product delivers value?
(choose the best three answers)
True or False: During the Sprint Review the stakeholder's role is to reorder the Product Backlog.
A Scrum Master is working with a Scrum Team that has Developers in different physical
locations. The Developers meet in a variety of meeting rooms and have much to do logistically
(for example: reserve meeting rooms and set up conference calls) before the Daily Scrum.
What action should the Scrum Master take?
(choose the best answer)
Who is accountable for creating a valuable and usable Increment each Sprint?
(choose the best answer)
Who is accountable for managing the progress of work during a Sprint?
(choose the best answer)
How is management that is external to the Scrum Team involved in the Daily Scrum?
(choose the best answer)
How much time is required after a Sprint to prepare for the next Sprint?
(choose the best answer)