Questions # 131:

What technique does TOGAF recommend for evaluating the status of an organization to undergo change?

Options:

A.

Business Transformation Readiness Assessment

B.

Business Value Assessment Technique

C.

Capability-Based Planning

D.

Communications and Stakeholder Management

E.

Gap Analysis

Questions # 132:

Which one of the following best describes the purpose of the Communications Plan?

Options:

A.

To act as a deliverable container for artifacts created during a project

B.

To ensure that information is communicated to the right stakeholders at the right time

C.

To ensure that the results of a Compliance Assessment are distributed to the Architecture Board

D.

To inform the Architecture Board of changes to the architecture

E.

To show progression of change from the Baseline Architecture to the Target Architecture

Questions # 133:

What part of the TOGAF standard discusses the processes, skills and roles to operate an architecture function within an enterprise?

Options:

A.

Architecture Development Method

B.

Architecture Capability Framework

C.

Enterprise Continuum & Tools

D.

Architecture Content Framework

E.

TOGAF Reference Models

Questions # 134:

Consider the following image.

Question # 134

Complete the sentence: The assets in the B and C are structured from generic to specific to provide a consistent language to __________________.

Options:

A.

B = Architecture Building Blocks, C = Solutions Building Blocks, manage the volume of architecture content

B.

B = Business Architecture, C = Information Systems Solutions, define a taxonomy

C.

B = Architectures, C = Solutions, make it easier to understand conflicts

D.

B = Architecture Continuum, C = Solutions Continuum, communicate differences

Questions # 135:

In which Phase of the TOGAF ADM is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?

Options:

A.

Phase F

B.

Phase D

C.

Phase G

D.

Phase E

E.

Phase A

Questions # 136:

What are the following activities part of?

• Risk classification

• Risk identification

• Initial risk assessment

Options:

A.

Security Architecture

B.

Risk Management

C.

Phase G

D.

Phase A

Questions # 137:

According to TOGAF, in which sequence should Application Architecture and Data Architecture be developed in Phase C?

Options:

A.

Application Architecture should be developed first, then Data Architecture

B.

Application Architecture should be developed concurrently with Data Architecture

C.

Data Architecture should be developed first, then Application Architecture

D.

Application Architecture and Data Architecture may be developed in either sequence

Questions # 138:

The TOGAF ADM uses a version numbering convention to illustrate the evolution of Baseline and Target Architecture Definitions. What does Version 1.0 indicate according to this convention?

Options:

A.

A high-level outline architecture

B.

A preliminary outline architecture

C.

A formally reviewed, detailed architecture

D.

A draft, detailed architecture

E.

A formally reviewed, preliminary architecture

Questions # 139:

According to TOGAF, which of the following best describes Architecture Governance?

Options:

A.

A categorization mechanism for architecture and solution artifacts

B.

A framework for operational and change activity

C.

A method for designing an information system in terms of a set of building blocks

D.

The lifecycle management of information and related technology used by an organization

E.

The practice by which enterprise architectures are controlled at an enterprise-wide level

Questions # 140:

According to TOGAF, which document should incorporate the actions arising from the Business Transformation Readiness Assessment technique?

Options:

A.

Architecture Road map

B.

Architecture Requirements Specification

C.

Communications Plan

D.

Implementation and Migration Plan

E.

Implementation Governance Model