Questions # 51:

Scenario:

Please read this scenario prior to answering the question

Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.

The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.

Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.

The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.

Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.

Refer to the Scenario

The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete. You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the less

B.

You would assess how the plan impacts the other frameworks in use in the organization. Minimally, the plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. You would then assign a business value to each project, taking into account available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.

C.

You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identi

D.

You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Arc

Expert Solution
Questions # 52:

Which part of the TOGAF standard provides a full description of each architecture phase?

Options:

A.

Architecture Capability Framework

B.

Architecture Development Method

C.

ADM Guidelines and Techniques

D.

Enterprise Continuum & Tools

Expert Solution
Questions # 53:

Please read this scenario prior to answering the question

You are serving as the Lead Architect for an Enterprise Architecture project team

within a multinational energy company. The company is organized into two major

business operations:

· Upstream operations which include exploration for crude oil and natural gas and

operating the infrastructure necessary to deliver oil and gas to the market

· Downstream operations which include the manufacturing, distribution and marketing

activities for oil products and chemicals

The downstream business includes oil refining, a retail filling station network,

lubricants manufacture and marketing, industrial fuel and lubricants sales. The

practice for the downstream business has been to operate locally, managed by local

"operating companies".

There is an established Enterprise Architecture program within the company, and the

TOGAF standard has been adopted as the framework.

Safety is a priority for the company, with the aim to ensure it causes zero harm to

people and the environment. The company has to satisfy the regulatory requirements

of each of the countries it operates in.

The Governing Board is concerned about the risk posed by operating in this complex

global environment with a large part of the downstream business represented by local

operating companies.

The Chief Executive Officer (CEO) has requested to be informed about the status of

downstream operations that could impact regulatory compliance. He also wants the

corporate legal staff and auditors to analyze all proposed new downstream operations

to ensure that they are within the legal guidelines for each country. In addition, the

local operating companies should be able to see that the architecture is appropriate

for their needs.

The architecture project team has completed a detailed Request for Architecture Work

providing the high level project description. As the project commences the next phase,

the necessary approvals from management have been received.

Refer to the Scenario

You have been asked to recommend an approach that would enable the development

of an architecture that addresses the needs of the Chief Compliance Officer, legal

staff, auditors and the local operating companies.

Based on the TOGAF Standard, Version 9.2, which of the following is the best

answer?

Options:

A.

You recommend that a Communications Plan be created to address the

powerful and influential stakeholders identified in a stakeholder power grid

matrix. This plan should include a report that summarizes the key features of

the architecture with respect to each location and reflect the stakeholder

requirements. You will check with each stakeholder that their concerns are

being addressed.

B.

You recommend that an Organization Map is created to show the relationships

between the different operations within the company and the local operating

companies. This will be used to identify key stakeholders. A set of models

should then be developed that can be applied uniformly across the project. The

stakeholders can then examine the models to ensure that their needs have

been addressed.

C.

You recommend that a stakeholder analysis is made, so as to identify which

stakeholders are involved, their level of involvement, and their concerns. This

will allow the architects to define groups of stakeholders who have common

concerns. The concerns and relevant viewpoints should then be defined for

each group of stakeholders, and recorded in the Architecture Vision document.

D.

You recommend that an analysis of stakeholders occurs, with 22 types of

stakeholders identified, in five categories - corporate functions, end-user

organization, project organization, systems, and external. Models should then

be created for each stakeholder category to ensure that the system complies

with the local regulations. A formal review should be held with the stakeholders

to verify that their concerns h

Expert Solution
Questions # 54:

Scenario

Please read this scenario prior to answering the Question

You are serving as the Lead Architect for an enterprise architecture project team within a leading multinational pharmaceutical and medical devices manufacturer. Its brands include numerous household names for medications and first aid supplies.

The company has a long history of innovating new treatments for many common illnesses and diseases. Prior to launching a new treatment, the company has to demonstrate Its effectiveness and safety in a set of clinical trials that satisfy the regulatory requirements of the countries in the target markets. All clinical trials are undertaken by its research laboratories, which employ over 10,000 people at separate facilities in the United Kingdom, United States, Sweden, France, Canada, India, China and Japan. In addition to internal research and development activities the company is also involved in publicly funded collaborative research projects, with other industrial and academic partners.

The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners.

The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners.

The Enterprise Architecture group is a mature organization. They use the TOGAF 9 ADM with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant.

The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. She has stated that the changes to the enterprise architecture for the new system will need to be rolled out in stages on a regional basis that minimizes disruptions to ongoing clinical trials.

Refer to the Scenario

You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).

Based on TOGAF, which of the following is the best answer?

Options:

A.

Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRUD matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule

B.

Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability

C.

Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. Document the progression of the enterprise architecture using a state evolution tabl

D.

Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.

Expert Solution
Questions # 55:

Scenario:

Please read this scenario prior to answering the Question

You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.

The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.

TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario

In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.

B.

You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security

C.

You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees. You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security

D.

You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being de

Expert Solution
Questions # 56:

Which of the following best describes the Standards Information Base?

Options:

A.

A repository area that defines the parameters, structures, and processes to support governance.

B.

A repository area that describes the organization specific architecture framework and methodologies.

C.

A repository area that provides guidelines, templates, and pattern used to create new architectures.

D.

A repository area that lists a set of specifications to which architectures must conform

E.

A repository area that provides a record of the governance activity across the enterprise.

Expert Solution
Questions # 57:

Scenario:

Please read this scenario prior to answering the question

The ABC company is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business.

The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture. The company has selected TOGAF 9 as the basis for its Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario

You are serving as the Chief Architect.

You have been asked to recommend the approach to take in the Preliminary Phase to ensure that the Corporate Board's concern is addressed.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You evaluate the implications of the Board's concern in terms of regulatory and security policy requirements. You then update the company security policy to reflect the concern, ensuring that this policy is communicated across the organization.You allocate a security architecture team to ensure that security considerations are included in ongoing architecture planning. You then assess the security implications and agreements within the comp

B.

You start by clarifying the intent that the Board has for raising this concern. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture.

C.

You evaluate the implications of the Board's concern in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the Board's concern. You allocate a security architect to oversee the implementation of the solution in the ERP system that is being develop

D.

You evaluate the implications of the Board's concern by examining the potential impacts on business goals and objectives. Based on your understanding, you then update the current company security policy to include an emphasis on the Board's concern.In addition, you allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.

Expert Solution
Questions # 58:

You are an Enterprise Architect working at a vehicle manufacturing company. The company specializes in buses and coaches. You are part of an Enterprise Architecture (EA) team that has responsibilities across multiple divisions of the company.

The company has a corporate strategy that focuses on switching to electric power for its vehicles. It has invested heavily in a new standardized design, production efforts, and major components to use across all its product range. The company has multiple manufacturing plants in North America, Europe, and Asia.

Customer demand has caused a backlog of orders because many customers want to have more environmentally friendly public transportation. There are not enough electronic components available, which is making it hard to produce products and meet customer demand. To address this issue, the company has started making the battery packs themselves and has hired new suppliers.

The company has a well-established EA practice. It uses the TOGAF Standard as the foundation for its work, including the internal EA framework. Additionally, the company uses various management frameworks such as business planning, project management, and operations management. The Chief Information Officer (CIO) and the Chief Operating Officer (COO) jointly sponsor the Enterprise Architecture program.

The EA team is working on a project to improve the process and systems to design, produce, and test the battery pack. As part of putting the new battery pack into production, changes to the assembly processes need to be made. A trial has been completed at a single location. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan to roll out these changes to all plants.

Preliminary Architecture Contracts have been developed that detail the work needed to put in place the new processes for each location. The company mixes internal teams with a few third-party contractors at the locations. The Chief Engineer is worried that the deployment will not be consistent and of satisfactory quality.

Refer to the scenario:

The EA team leader has asked you to review the preliminary Architecture Contracts and recommend the best approach to address the Chief Engineer's concern.

Options:

A.

You check the contracts ensuring that they address project objectives, effectiveness metrics, acceptance criteria, and risk management. Third-party contracts must be legally enforceable. You advise that there be a schedule of compliance reviews at key points in the implementation process. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the

B.

You recommend that the Architecture Contracts be used to manage the architecture governance processes across the locations. You recommend deployment of monitoring tools to assess the performance of each completed battery pack at each location and develop change requirements if necessary. If a deviation from the contract is detected, the Architecture Board should allow the Architecture Contract to be modified to meet the local needs. In such

C.

For changes requested by an internal team, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to third-party contractors, you recommend that it is a fully enforceable legal contract. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the implementation organizat

D.

For changes undertaken by internal teams, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. If a contract is issued to a contractor, you recommend that it is a fully enforceable legal contract. If a deviation from the Architecture Contract is found, you recommend that the Architecture Board grant a dispensation to allow the implementation organization to customize the process to

Expert Solution
Questions # 59:

Which of the following best describes the purpose of the Architecture Roadmap?

Options:

A.

It lists work packages on a timeline showing progress towards the Target Architecture

B.

It contains an assessment of the current architecture requirements

C.

It provides for effective communication of the end architecture project to the stakeholders

D.

It forms the basis of a contractual agreement between the sponsor and the architecture organization

E.

It is sent from the sponsor and triggers the start of an architecture development cycle

Expert Solution
Questions # 60:

Which of the following describes an objective of the Preliminary Phase?

Options:

A.

Ensure conformance requirements for the target architecture are defined

B.

Develop the Implementation and Migration Plan

C.

Operate the governance framework

D.

Establish the architecture governance processes

E.

Develop the Architecture Vision document

Expert Solution