Questions # 111:

Which of the following Water Efficiency credits differ between LEED Building Design and Construction: New Construction and LEED Building Design and Construction: Healthcare?

Options:

A.

LEED Building Design and Construction: Healthcare has no Water Efficiency Credit, Cooling Tower Water Use

B.

LEED Building Design and Construction: New Construction has no Water Efficiency Credit, Cooling Tower Water Use

C.

LEED Building Design and Construction: Healthcare has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

D.

LEED Building Design and Construction: New Construction has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

Questions # 112:

A new Science Education Center is pursuing LEED certification. Which of the following strategies could be submitted to earn an Innovation in Design credit?

Options:

A.

The selection of energy-efficient LED fixtures for all of the building's lighting

B.

The installation of an air-purifying facade material on the front entrance of the building

C.

The integration of rainwater management strategies to achieve a Regional Priority Credit

D.

The implementation of a comprehensive metering strategy to measure three individual energy end uses

Questions # 113:

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Questions # 114:

How can the additional energy needed to increase the ventilation in a building be mitigated?

Options:

A.

Use economizer strategies

B.

Use higher-rated MERV filters

C.

Use high-pressure drop filters

D.

Reduce the size of the ventilation ductwork

Questions # 115:

The LEED AP is leading the first design charrette for a new LEED project with the project's owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner's Project Requirements (OPR)

B.

Owner's list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Questions # 116:

Which of the following methods is the referenced standard for demonstrating compliance with Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Options:

A.

ASHRAE 62.2 - 2007

B.

ASHRAE 90.1 - 2010

C.

ASHRAE 55 - 2010

D.

ASHRAE 62.1 - 2010

Questions # 117:

LEED project boundaries that include multiple similar buildings which are all eligible for certification can be registered as which of the following?

Options:

A.

Batch project

B.

Group project

C.

Master Site project

D.

Neighborhood project

Questions # 118:

How much value would these two doors contribute toward Material and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

Options:

A.

$150.00

B.

$50.00

C.

$100.00

D.

$125.00

Questions # 119:

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

Options:

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

Questions # 120:

Which of the following strategies supports energy resilience by enhancing the grid interactivity of a building?

Options:

A.

Install smart meters to provide real-time data on energy consumption

B.

Install energy-storage systems that can deploy energy during peak-demand periods

C.

Use occupancy sensors to turn lights on and off automatically

Viewing page 12 out of 13 pages