Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the AACE International AACE Certification CCP Questions and answers with ValidTests

Exam CCP All Questions
Exam CCP Premium Access

View all detail and faqs for the CCP exam

Viewing page 3 out of 6 pages
Viewing questions 21-30 out of questions
Questions # 21:

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Total float

B.

Remaining duration

C.

Free float

D.

Just-in-time scheduling

Expert Solution
Questions # 22:

Question # 22

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, the final price for the piece of equipment will be:

Options:

A.

$328,810

B.

$370,710

C.

$375,658

D.

$378,750

Expert Solution
Questions # 23:

If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

Options:

A.

$2,424

B.

$2,976

C.

$2,688

D.

$2,697

Expert Solution
Questions # 24:

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?

Options:

A.

1

B.

1.04

C.

0.89

D.

0.96

Expert Solution
Questions # 25:

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

Question # 25

What is the median unit cost?

Options:

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Expert Solution
Questions # 26:

Question # 26

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs from Atlanta, GA?

Options:

A.

$40.59

B.

3

C.

$48.33

D.

33.33%

Expert Solution
Questions # 27:

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

Options:

A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Expert Solution
Questions # 28:

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual estimated tax would be:

Options:

A.

$3,869

B.

$5,565

C.

$10,500

D.

$11,925

Expert Solution
Questions # 29:

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

Options:

A.

Project is ahead of schedule, but over budget

B.

Project is behind schedule, but over budget

C.

Project is behind schedule, but under budget

D.

Project is ahead of schedule, but under budget

Expert Solution
Questions # 30:

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

Options:

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Expert Solution
Viewing page 3 out of 6 pages
Viewing questions 21-30 out of questions