Questions # 91:

A project communication plan identifies the relevant information that should be communicated to:

Options:

A.

the project team.

B.

the project stakeholders.

C.

the project board.

D.

the project sponsor

Expert Solution
Questions # 92:

Estimating by using historical information is known as:

Options:

A.

comparative estimating.

B.

parametric estimating.

C.

bottom-up estimating.

D.

strategic estimating.

Expert Solution
Questions # 93:

Which of the following actions would not help a team leader influence the performance of their team?

Options:

A.

Creating an exclusive environment.

B.

Providing clear roles and responsibilities.

C.

Promoting openness and honesty.

D.

Developing a trusting relationship.

Expert Solution
Questions # 94:

Which of the following descriptions particularly identifies a risk?

Options:

A.

An unplanned delay to the project.

B.

A. current problem that will result in the project going over budget.

C.

An uncertain event that if it occurs will have an effect on one or more of the project objectives,

D.

A. current problem that will result in the project being delayed.

Expert Solution
Questions # 95:

Which one of the following statements best describes resource scheduling?

Options:

A.

A. process which identifies activities that will need project resources.

B.

A. process to assign roles to project resources.

C.

A. process that identifies when resources are needed.

D.

A. process to estimate the project resources.

Expert Solution
Questions # 96:

The purpose of a decision gate is to decide whether:

Options:

A.

the response to a risk is valid.

B.

a project is viable in line with the business case.

C.

the project delivered against the success criteria.

D.

lessons were effectively learned during the project.

Expert Solution
Questions # 97:

What is the main aim of the communication plan?

Options:

A.

To increase the chances of achieving effective engagement.

B.

To comply with the structure of the project management plan.

C.

To identify the skills necessary to deliver a project.

D.

To increase the likelihood of benefits realisation.

Expert Solution
Questions # 98:

A project is typically defined in terms of scope, time, cost and which other parameter?

Options:

A.

Benefits.

B.

Quality.

C.

Tolerance.

D.

Controls.

Expert Solution
Questions # 99:

When is it best to carry out a benefit review?

Options:

A.

At 6—12 months after handover.

B.

At various stages prior to handover.

C.

At the concept phase when developing the business case

D.

At various stages through deployment

Expert Solution
Questions # 100:

Which one of the following is captured in the Work Breakdown Structure (WBS)?

Options:

A.

The life cycle phases.

B.

The logical order of tasks.

C.

The scope of the project.

D.

Project costs.