Questions # 111:

The purpose of a risk register is to provide a:

Options:

A.

structured process for risk identification.

B.

record of the ownership of risk and issue management actions.

C.

means of assessing the likelihood and impact of all of the risks.

D.

record of risks, their impact and the actions taken to manage them.

Expert Solution
Questions # 112:

When are benefits usually realised when using an iterative life cycle?

Options:

A.

During the project

B.

Post project

C.

At project closure

D.

Both during and after the project

Expert Solution
Questions # 113:

PESTLE analysis covers the following areas:

Options:

A.

Political, Economic, Sociological, Technical, Legal, Environmental.

B.

Personnel, Economic, Safety, Technical, Legal, Ecological.

C.

Political, Ecological, Strategy, Technical, Life cycle, Environmental.

D Personnel, Ecological, Sociological, Training, Life cycle, Ecological.

Expert Solution
Questions # 114:

Where in the project life cycle would the project manager typically be appointed?

Options:

A.

At the start of the concept phase.

B.

At the start of the definition phase.

C.

At the start of the development phase.

D.

At the end of the handover stage.

Expert Solution
Questions # 115:

Which one of the following is an example of a project issue?

Options:

A.

There are no suppliers that can meet our specification.

B.

We may not be able to finish on time.

C.

The project is going to be late.

D.

A key phase of the project is taking longer than expected

Expert Solution
Questions # 116:

The purpose of quality assurance is to:

Options:

A.

provide confidence the project will satisfy the relevant quality standards.

B.

determine a set of procedures and standards for project management.

C.

inspect, measure and test deliverables and processes.

D.

define the scope and specifics of a project's deliverables

Expert Solution
Questions # 117:

What is the main reason for an initial high-level review of a change request?

Options:

A.

To consider if the change is feasible to evaluate at this stage.

B.

To establish who might be the best stakeholders to be involved in the change.

C.

To ensure that the change request is considered as soon as possible.

D.

To implement the necessary actions to ensure the change has a smooth implementation.

Expert Solution
Questions # 118:

The primary purpose of a milestone in a project is to show:

Options:

A.

significant events.

B.

resource constraints.

C.

task dependencies.

D.

critical path highlights.

Expert Solution
Questions # 119:

While providing support to the project and attending a risk management workshop, the following statements were noted. Which one of these could be considered as a risk to a project?

Options:

A.

We have never done a project of this kind before.

B.

We might not have sufficient people with the right experience to undertake the project.

C.

We always find that design verification takes longer than planned.

D.

We have never worked in that country before.

Expert Solution
Questions # 120:

Which of the following are the major stakeholders of the project management plan?

1) Project sponsor

2) General public

3) Project team

4) Project manager

Options:

A.

1, 2 and 4

B.

1, 2 and 3

C.

1, 3 and 4

D.

2, 3 and 4

Expert Solution