Questions # 11:

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Expert Solution
Questions # 12:

Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?

Options:

A.

No, because the FIDIC procurement process is universal.

B.

No, because Employers never have specific procurement rules.

C.

Yes, based on the law system, internal governance or type of Employer additional procurement rules can apply.

D.

Yes, but this is only applicable for public entities like governments. If the Employer is a private organisation (like a company), they are free to procure how they want.

Expert Solution
Questions # 13:

The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If the advance payment is not completely repaid before Time for Completion.

B.

If advance payment is not completely repaid before the Performance Certificate is issued.

C.

If the advance payment is not completely repaid before the Taking-Over Certificate is issued.

D.

If the advance payment is not completely repaid before termination of the Contract.

Expert Solution
Questions # 14:

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.

B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.

C.

Any amounts to be added and deducted for changes in legislation and changes in cost.

D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.

Expert Solution
Questions # 15:

Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?

Options:

A.

Amending clauses, supposedly in the interest of the Employer, immediately nullifies all the advantages of standardization, and almost invariably introduces conflicting or ambiguous requirements on the parties, and often causes mistrust between them.

B.

The FIDIC Books provide people who draft contracts with great examples on how to draft a good contract model. Furthermore, arrangements from Red, Yellow and Silver Books can be easily mixed to get a good fit for a specific project.

C.

The Form of Contract is chosen by the Contractor and imposed by him on the Employer, who tenders on that basis.

D.

People who draft contracts should, when preparing a new contract, always start with the question: where do I want to lay the most risks between Employer and Contractor, and does the Employer has the budget to reward Contractors with a high risk apatite?

Expert Solution
Questions # 16:

Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor is responsible for the performance of the Nominated Subcontractors

B.

Deletion of Sub-Clauses 20.2 - 20.4 for a Project constructed in United Arab Emirates

C.

The DAB Decision is final and binding

D.

The Payment shall be released by the Employer within 180 days calculated from receiving the Contractor's Monthly Statement

Expert Solution
Questions # 17:

Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

Options:

A.

Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.

B.

The Contractor cannot terminate the Contract.

C.

The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.

D.

The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.

Expert Solution
Questions # 18:

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor failed to renew the Tender Security.

B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.

C.

The Employer had submitted a claim under Sub-Clause 20.2.

D.

The Engineer had issued instruction to replace part of the Works.

E.

The Contractor failed to extend the validity of the Performance Security.

Expert Solution
Questions # 19:

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

Options:

A.

True

B.

False

Expert Solution
Questions # 20:

What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Notice is a defined term, while other communications are not defined as a term in the General Conditions.

B.

Contractually there is no difference between a notice and other communications.

C.

Both 'Notice' and 'Other Communications' are defined terms under the Conditions of Contract.

D.

The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.