The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.
Is this statement true or false?
You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?
Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?
Choose all of the correct answers (multiple possibilities)
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
Which one of the following statements is correct regarding the Employer's Representative under the FIDIC Silver Book (edition 1999)?
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?
Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]
(2 correct answers apply)
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).