Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the GIAC GCPM Questions and answers with ValidTests

Exam GCPM All Questions
Exam GCPM Premium Access

View all detail and faqs for the GCPM exam

Viewing page 5 out of 12 pages
Viewing questions 41-50 out of questions
Questions # 41:

Which of the following are the tasks performed by the Work breakdown structure (WBS)?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

It separates the major project deliverables into smaller components to improve the accuracy of cost estimates.

B.

It defines assignable resources, such as personnel, from a functional point of view.

C.

It provides a mechanism for collecting and organizing actual costs.

D.

It provides a mechanism for performance measurement and control.

Expert Solution
Questions # 42:

You work as a project manager for PassGuide Inc. Which of the following stages of the process group, if not performed well by you, is unlikely that the project will be successful in meeting the business needs?

Options:

A.

Executing

B.

Planning and design

C.

Initiation

D.

Monitoring and controlling

Expert Solution
Questions # 43:

You work as a project manager for PassGuide Inc. Which of the following processes will you use to build up an estimate of the monetary resources required to complete project activities?

Options:

A.

Determine budget

B.

Control costs

C.

Estimate costs

D.

Plan quality

Expert Solution
Questions # 44:

Your project is an agricultural-based project that deals with plant irrigation systems. You have discovered a byproduct in your project that your organization could use to make a profit. If your organization seizes this opportunity it would be an example of what risk response?

Options:

A.

Opportunistic

B.

Positive

C.

Exploiting

D.

Enhancing

Expert Solution
Questions # 45:

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?

Options:

A.

1.23

B.

$524,000

C.

.80

D.

100 percent because the vendor caused her lateness

Expert Solution
Questions # 46:

You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?

Options:

A.

Mitigation

B.

Transference

C.

Acceptance

D.

Sharing

Expert Solution
Questions # 47:

You work as a project manager for PassGuide Inc. Your project has a budget of $545,000 and is expected to last 12 months. You have identified several risk events and created risk response plans for your project. In which of the following process groups will you be able to implement risk response plans?

Options:

A.

Planning

B.

Initiating

C.

Executing

D.

Monitoring and controlling

Expert Solution
Questions # 48:

You are the project manager for your organization. Your organization manages projects for other companies. You will be soon managing a project for the JUH Company. What document do you need first to help to develop the project charter?

Options:

A.

Business requirements

B.

Functional requirements

C.

Preliminary project scope statement

D.

Contract

Expert Solution
Questions # 49:

You are the project manager for your organization. Marcy, a project stakeholder, is demanding that you add some deliverables to your project scope for free. You explain to Marcy that it's too late in the project execution to consider adding these deliverables, as most of the software your project team is creating is nearly done. Marcy and you escalate the issue to management. Management decides that you will add the deliverables to the project scope if Marcy pays a significant fee and allows you additional time to complete the project. What conflict resolution method has management offered?

Options:

A.

Confronting

B.

Issue management

C.

Compromising

D.

Forcing

Expert Solution
Questions # 50:

Which of the following is described in the statement below?

"It is an approved time-phased budget that monitors and measures cost performance throughout the project life cycle."

Options:

A.

Cost baseline

B.

Scope baseline

C.

Cost budgeting

D.

Cost estimation

Expert Solution
Viewing page 5 out of 12 pages
Viewing questions 41-50 out of questions