Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the ISTQB Foundation Level ISTQB-CTFL Questions and answers with ValidTests

Exam ISTQB-CTFL All Questions
Exam ISTQB-CTFL Premium Access

View all detail and faqs for the ISTQB-CTFL exam

Viewing page 4 out of 13 pages
Viewing questions 31-40 out of questions
Questions # 31:

Which test approach will best fit a new project, with little documentation and high probability for bugs?

Options:

A.

Exploratory testing

B.

Requirements based testing

C.

Metric based approach

D.

Regression testing

Expert Solution
Questions # 32:

Which of the following is a role that is usually responsible for documenting the findings (e.g., action items, decisions, recommendations) made by the review team as part of a typical formal review?

Options:

A.

Review leader

B.

Facilitator.

C.

Recorder.

D.

Moderator

Expert Solution
Questions # 33:

Which of the following can be considered a VALID exit criterion?

I Estimates of defect density or reliability measures.

II. The completion and publication of an exhaustive Test Report.

III. Accuracy measures, such as code, functionality or risk coverage.

IV Residual risks such as lack of code coverage in certain areas.

Options:

A.

I, III, IV

B.

I, II, III

C.

III, IV

D.

II, III, IV

Expert Solution
Questions # 34:

A software system checks age in order to determine which welcome screen to display. Age groups are:

Group I: 0-12

Group II; 13-18

Group III: over 18

Which of the below represent boundary values?

Options:

A.

(-1.0.12.13.18,19)

B.

(-1.0,11.12.13,14,18.19)

C.

(0.12.13.18.19)

D.

(4.5.15.20)

Expert Solution
Questions # 35:

A test engineer finds a defect while testing. After the developer has fixed the defect, the test engineer decides to re-run a complete section of the tests. Which of the following is correct?

Options:

A.

The lest engineer should not re-run the tests, as they have already been run, and results recorded.

B.

The test engineer should not re-run the tests, they should be part of the developer tests.

C.

The test engineer should re-run the tests, in order to ensure that new defects have not been introduced by the fix.

D.

The test engineer should re-run the tests, because the defect shows that the test cases need to be updated.

Expert Solution
Questions # 36:

While repotting a defect, which attribute indicates the degree of impact that the defect has on the system?

Options:

A.

Priority

B.

Severity

C.

Status

D.

Description

Expert Solution
Questions # 37:

You are testing the download process of a mobile phone application.

For which to the following capabilities to the system you need to design a nonfunctional test?

Options:

A.

It was easy to locate, download and install the application

B.

The application was correctly downloaded

C.

The application created an installation log file in a given folder

D.

The application installed only after the user's approval

Expert Solution
Questions # 38:

As the last stage of a test cycle of an embedded device, you are performing exploratory testing. You observed that some character. (A, X andZ)sent via a serial port to the device do not get registered on the device whereas they should be. You suspect that this could be due to a wrong configuration of the "bit parity" parameter.

Which of the following items of an incident report would you beUNABLEto write down based on this information?

Options:

A.

Expected result

B.

Test case identifier

C.

Test setup details

D.

Actual result

Expert Solution
Questions # 39:

Which or the following is a valid collection of equivalence classes for the following problem: An integer field shall contain values from and including 1 to and including 15.

Options:

A.

Less than 0.1 through 14. 15 and more

B.

Less than 1.1 through 14. more than 15

C.

negative numbers. 1 through 15. above 15

D.

Less than 1.1 through 15. more than 15

Expert Solution
Questions # 40:

A program is used to control a manufacturing line (turn machines on and off. start and stop conveyer belts, add raw materials to the flow. etc.). Not all actions are possible at all times. For example, there are certain manufacturing stages that cannot be stopped - unless there is anemergency. A tester attempts to evaluate if all such cases (where a specific action is not allowed) are covered by the tests.

Which coverage metric will provide the needed information for this analysis?

Options:

A.

Code coverage

B.

Data flow coverage

C.

Statement coverage

D.

Branch Coverage

Expert Solution
Viewing page 4 out of 13 pages
Viewing questions 31-40 out of questions