Questions # 21:

Optimizing the portfolio is a major recurring process that the portfolio manager performs throughout the portfolio life cycle in order to balance the mix of portfolio components. During this process, the portfolio manager uses a number of graphical analytical methods to help him ease the process. Which of the following is not a graphical analytical method used in this process?

Options:

A.

Pie Charts

B.

None of the options

C.

Risk vs. Return charts

D.

Histograms

Expert Solution
Questions # 22:

The portfolio undergoes a lot of changes through the portfolio life cycle, and the state of the portfolio changes on the go. Some components are terminated, other are added and initiated. When it comes to the authorize portfolio process, which of the following represents the state of the portfolio

Options:

A.

List of current components that need to be weighted, scored and ranked

B.

List of selected and balanced components

C.

List of strategically aligned portfolio components without the need for them to be balanced

D.

List of selected, balanced and authorized components ready to be initiated

Expert Solution
Questions # 23:

It is rare for organizational leaders to have an in-depth knowledge of all the work under way in the portfolio, but it is needed for portfolio decision making. If you were asked to prepare such an inventory, it would:

Options:

A.

Require one-on-one interviews to ensure all work being done was revealed

B.

Be helpful to have a statement in writing from the CEO to describe why the inventory is important

C.

Serve as the starting point for the portfolio

D.

Require assistance and support from the EPMO

Expert Solution
Questions # 24:

A key role for portfolio management is to balance the use of resources following the need against the existing skill-set. One of the component managers told you that an important SME on his program is traveling and there is no replacement for her. This will cause a major delay in the program. What is your first step as a portfolio manager?

Options:

A.

Do interdependency management and see the impact

B.

Send a broadcast report to all components informing them of the issue

C.

Ask him to do a quick recruitment and hire someone to solve the issues

D.

Tell him that he needs to find out a solution and that you will be ready for any assistance needed

Expert Solution
Questions # 25:

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. While planning for risk management, multiple investment choice tools are used as part of the quantitative and qualitative analyzes. Which of the following tools determine the effect of changing the portfolio?

Options:

A.

Budget Variability

B.

Market Payoff variability

C.

Performance variability

D.

Trade-Off Analysis

Expert Solution
Questions # 26:

Assume you are preparing the first portfolio risk management plan for your outsourcing company, which typically handles call centers around the world. While the company has implemented portfolio management and has a Portfolio Oversight Group, it did not previously assess risks to the portfolio itself. Instead, it assumed risks would be managed at the project level. However, numerous customer complaints have been received. The root cause is once a new call center is established, limited if any planning is done as the manager rushes to have it ready and operational as soon as possible. This has led to a lack of understanding as to what is required for the call centers to be successful. In preparing this plan, you are reviewing the portfolio management plan because it:

Options:

A.

Contains the portfolio vision statement

B.

Provides the organization's risk tolerance

C.

Provides guidance on stakeholder engagement

D.

Includes the portfolio performance matrices

Expert Solution
Questions # 27:

Along your portfolio lifecycle, you have been conducting multiple review meetings to ensure continuation from one phase to another and to ensure the alignment and value delivery, in addition to communicating decisions and valuable information to the related stakeholders. Changes to the approach of portfolio governance may be a result of review meetings. Which of the following options include updates to the governance model?

Options:

A.

Portfolio Management Plan updates

B.

Portfolio Process Assets updates

C.

Portfolio Reports

D.

Portfolio Strategic Plan updates

Expert Solution
Questions # 28:

Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently in the process of monitoring the portfolio to ensure alignment with organizational strategy and objectives and make governance decisions. What do you expect as an outcome to this?

Options:

A.

Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Organizational Process Assets update

B.

Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process Assets update

C.

Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Organizational Process Assets update, Portfolio Process Assets update

Portfolio Updates, Portfolio Strategic Plan updates, Portfolio Reports, Organizational Process Assets update, Portfolio Process Assets update

Expert Solution
Questions # 29:

Assume you are the portfolio manager for the Federal Railroad Administration. Funding is provided annually according to the Government's budget process. Any monies that are not spent at the end of a fiscal year are lost, and there are some restrictions in place concerning whether funds can be transferred to different programs, projects, or operations work in the agency. Therefore, to maximize the use of funding you require:

Options:

A.

Regular reports on funds for authorized components

B.

Projections on a quarterly basis as to the funds components require

C.

Mechanisms for internal audits to ensure funds are allocated effectively

D.

Accurate estimates of the funds needed when the component is proposed for consideration

Expert Solution
Questions # 30:

Working to monitor the portfolio especially in terms of its value to the organization, you had each component manager prepare monthly variance reports. Of the components ranked in the top 10, six of them realized they would not require some of their initial funding and still would be completed as planned. This means:

Options:

A.

Three-point estimating should be used as funds are allocated

B.

Next year's budget can be adjusted

C.

Historical data would be useful on estimates versus actual costs

D.

The amount of contingency and management reserves can be decreased

Expert Solution