After the second shutdown of the Government, your Agency Administrator realized that some essential programs had to continue even during the shutdown, some existing work along with some programs and projects in the pipeline perhaps were not needed, and resources may require reallocation. This example shows the:
Assume you are the portfolio manager for a company that specializes in software, including portfolio management software. It has many components under way to enhance the existing product line but also to move the company into Cloud computing. You regularly prepare reports on the portfolio status but lately have had a large number of stakeholders request ad hoc reports. You decided to survey your stakeholders to learn about their information needs. You next decided to hold some one-on-one interviews with several interested and influential stakeholders in terms of communications requirements. From these interviews you are concerned that some stakeholder groups may be missing so you decided to:
Managing Strategic Change is an integral part of any portfolio in order to remain aligned with the strategic objectives. Your portfolio has undergone a major strategic change and you are currently determining if, when, what, and how of implementing the change in order to re-align the portfolio. What are you currently doing?
Because of the ongoing and iterative nature of portfolio management, the processes in it are continually repeated as new components are added, and others are completed or terminated. Revisions are constant given complexity, risks, and the rate of change. As you work to optimize the portfolio, it is helpful to:
Your company acquired another company. The sponsor asked you to check the other company's current inventory of work and see what could be added to your current portfolio. You have a meeting coming up to show the sponsor the portfolio dependencies. Which document should you be showing him?
Your Portfolio Review Board is scheduled to meet in a week. Resources only are available to support one project, and detailed business cases have been prepared for two of them. Your company has a policy of being risk adverse. Based on the following table, which project would you recommend to the Board, and what else would you mention to them?

A portfolio manager needs to continuously balance the need and requirements with the available resources to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. When it relates to the organization level. This analysis comprises which of the following?
Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. When it comes to managing portfolio risks, which of the following activities is used
As part of the strategic alignment, you Rank strategic priorities working with key stakeholders and using qualitative and quantitative analyses in order to
Your executive management has been recently undergoing a change from a functional organization to a projectized one and is currently assessing the volume of work that the organization can execute. Which of the following tools and techniques will decide the volume of work and components that the organization can execute?